Vinca waste-to-energy project, Serbia
Name of the Project
Vinca waste-to-energy (WtE) project.
Location
The WtE facility and new landfill will be located in Vinca, alongside the existing landfill, about 15 km from Belgrade, Serbia.
Client
Beo Cista Energija, a joint venture between Suez Groupe, Itochu Corporation and Marguerite Fund II.
Project Description
The WtE facility will process residual municipal waste generated by 13 municipalities of the City of Belgrade, as well as construction and demolition waste (CDW) generated in its territory.
The project will include:
• an WtE facility processing up to 340 000 t/y of solid municipal waste, generating up to 29 MW of electricity to be supplied to the grid, and up to 56 MW of heat to the local district heating company;
• a 3.5 MW landfill gas-to-energy facility;
• a new sanitary landfill, designed to dispose up to 170 000 t/y of residual municipal waste;
• a leachate treatment plant for all effluents and leachate generated on site; and
• a CDW facility, comprising a crusher, sorting platform and landfill, to treat an estimated 200 000 t/y of waste. As part of the project, the company will also proceed with the closure of the existing Vinca dump site.
The project will also Include a 5 km, 110 kV, high-voltage transmission line to export the electricity and a 3.5 km medium-voltage transmission line to import the electricity.
The WtE facility will be connected and will deliver heat to the district heating system through an 8-km-long hot water pipeline that will be funded, permitted and constructed by the City of Belgrade.
Potential Job Creation
About 200 workers are expected to be employed during construction, with about 500 workers at peak. During operations, the workforce on site will be about 120.
Value
Total project cost is expected to be €339-million.
Duration
Construction is expected to take 36 months.
Latest Developments
None stated.
Key Contracts and Suppliers
None stated.
On Budget and on Time?
Too early to state.
Contact Details for Project Information
Beo Cista Energija, tel +381 11 715 4886 or email bce@bcenergy.rs.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation