Risk Mitigation Independent Power Producer Procurement Programme, South Africa – update

Image of a Karpowership

1st October 2021

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Risk Mitigation Independent Power Producer Procurement Programme (RMIPPPP).

Location
South Africa.

Project Owner/s
Department of Mineral Resources and Energy (DMRE).

Project Description
The RMIPPPP, also known as the ‘emergency’ procurement round, is a response to the short-term electricity supply gap identified in the Integrated Resource Plan 2019.

The objective of the RMIPPPP is to not only alleviate the current electricity supply constraints but also reduce the use of diesel-based peaking electrical generators.

The programme aims to procure 2 000 MW from a range of energy sources and technologies.

The DMRE issued a request for proposal for the RMIPPPP in August 2020.

Mineral Resources and Energy Minister Gwede Mantashe released the names of the eight preferred bidders on March 18, 2021:

  • the 150 MW ACWA Power Project DAO – a hybrid facility comprising solar photovoltaic (PV) and a battery energy storage system (BESS);
  • a 450 MW Karpowership SA Coega facility – a gas-to-power plant based on imported liquefied natural gas (LNG);
  • the 450 MW Karpowership SA Richards Bay facility – a gas-to-power plant based on imported LNG;
  • a 320 MW Karpowership SA Saldanha facility – a gas-to-power plant based on imported LNG;
  • the 198 MW Mulilo Total Coega facility – a hybrid plant employing solar PV and imported LNG;
  • the 75 MW Mulilo Total hydra storage project – a hybrid facility comprising solar PV and a BESS;
  • the 128 MW Oya Energy hybrid facility – a hybrid facility comprising solar PV, wind and a BESS; and
  • the 75 MW Umoyilanga Energy – a hybrid facility comprising solar PV, wind and a BESS.

In June 2021, the DMRE announced the appointment of three additional preferred bidder projects following the completion of “value for money” negotiations with Norwegian renewables power producer Scatec.

The Scatec projects will comprise three hybrid plants with solar PV technology and BESSs, in the Northern Cape.

To meet the dispatchable profile demanded under the RMIPPPP, the three projects – Kenhardt 1, Kenhardt 2 and Kenhardt 3 – will together produce 540 MW solar and 225 MW/1 140 MWh battery storage, based on sites in the Northern Cape.

Scatec has indicated that the projects are the only ones selected under the RMIPPPP that rely exclusively on renewable energy, making the three-project portfolio arguably one of the biggest single-site solar-storage hybrids in the world.

The projects will include average local content of 50% during construction, South African entity participation of 51% and black ownership of 41%.

Potential Job Creation
Not stated.

Capital Expenditure
The combined investment value of the eight projects is estimated at R45-billion.

Planned Start/End Date
The initial eight projects were expected to reach financial close by no later than the end of July 2021 and be connected to the grid from August 2022. However, the deadline for financial close has been shifted to September 30, owing to several processing delays.

The Scatec projects are required to achieve financial close by the end of September 2021, with grid connection by the end of 2022.

Latest Developments
The National Energy Regulator of South Africa (Nersa) has approved three generation licences for floating powership provider Karpowership during a special meeting of the energy regulator on September 21, 2021.

It also approved generating licences for four other energy producers under a scheme to fast-track new energy production.

Nersa has not yet released its reasons for the decision in full.

Karpowership still needs to obtain several other authorisations before it can moor its ships at the three ports and connect to the grid. In late June, it was refused environmental approval by the Department of Forestry, Fisheries and the Environment. Karpowership is confident that it will be granted approval on appeal.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
DMRE, Natie Shabangu, email natie.shabangu@dmre.gov.za; or Thandiwe Maimane, email thandiwe.maimane@dmre.gov.za.

 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

MBE Minerals SA (Pty) Ltd
MBE Minerals SA (Pty) Ltd

Your global lifecycle technology & service partner for materials & minerals processing equipment for coal, iron ore, copper, manganese & other...

VISIT SHOWROOM 
Alcohol Breathalysers
Alcohol Breathalysers

Supplier & Distributor of the Widest Range of Accurate & Easy-to-Use Alcohol Breathalysers

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.061 1.062s - 145pq - 2rq
Subscribe Now