Pisolite Hills bauxite mine and port project, Australia
Name and Location
Pisolite Hills bauxite mine and port project, Queensland, Australia.
Client
Cape Alumina.
Project Description
An updated prefeasibility study on the Pisolite Hills bauxite mine and port project has confirmed the technical and economic feasibility of the project as a bauxite mine delivering 7.5-million tonnes a year of dry product, producing high-quality, export-grade bauxite over a life of 14 years, based on a 134-million-tonne bauxite resource.
The proposed mine fleet includes front-end loaders and mine trucks, to load and transport the raw bauxite to the beneficiation plant, and road trains to transport the bauxite product to Port Musgrave.
Run-of-mine raw bauxite will be washed in three 650 t/h beneficiation plants, which incorporate crushing, sizing, screening and conveying.
Transshipping of the bauxite product is a key value driver for the operation and the use of 6 000 t to 10 000 t barges, loading 71 000 t Panamax or 166 000 t Cape-size vessels, has been incorporated into the design.
It is proposed that Pisolite Hills will start production at 2.5-million tonnes a year of dry beneficiated bauxite, building up to 7.5-million tonnes a year over two years.
Value
The project has a capital cost of $396-million.
Costs can be reduced through the implementation of contract mining, beneficiation, infrastructure ownership and operation, as well as synergies attributable to operating the project in conjunction with the Bauxite Hills project.
Duration
Not stated.
Latest Developments
Further optimisation work, including resource optimisation, will be undertaken to improve the project economics.
Key Contracts and Suppliers
None stated.
On Budget and on Time?
Too early to state.
Contact Details for Project Information
Cape Alumina, tel +61 7 3009 8000, fax +61 7 3221 4811 or email info@capealumina.com.au.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation