Northern Iron puts production in perspective

4th June 2013

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

  

Font size: - +

PERTH (miningweekly.com) – Iron-ore miner Northern Iron has lowered its production expectations for the current quarter to between 400 000 t and 425 000 t of dry concentrate, down from the previous guidance of 550 000 t at its Sydvaranger project, in Norway.

The miner has previously warned shareholders that the current quarter’s production would be affected by technical issues.

Northern Iron noted that the Sydvaranger project returned to normal operations on Monday, 14 days after experiencing a radial bearing failure. Concentrate production has now restarted and the company was focused on ramping up production to the higher rates experienced during February and March.

An investigation into the radial bearing failure has identified the cause as being a combination of procedural and process deficiencies in the control of the hydraulic system temperatures. During the course of the investigation, the issues were rectified and a reoccurance of this type of failure was not expected, the company said.

Northern Iron said on Tuesday that as a result of the production disruption and the general price weakness in the iron-ore market, the company was implementing further capital and operating cost reductions to help maintain liquidity.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Vikela Aluvin (Pty) Ltd
Vikela Aluvin (Pty) Ltd

Complete range of security sealing solutions including security seals bags and labels.

VISIT SHOWROOM 
CSIR International Convention Centre (CSIR ICC)
CSIR International Convention Centre (CSIR ICC)

CSIR International Convention Centre (CSIR ICC) - the leading conference and events venue in Pretoria/Tshwane.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.05 0.967s - 140pq - 2rq
Subscribe Now