Mozambique President inaugurates 120 MW gas-fired power station

Mozambique President Filipe Nyusi

Photo by Reuters

19th February 2016

By: Anine Kilian

Contributing Editor Online

  

Font size: - +

Mozambique President Filipe Nyusi on Friday inaugurated the 120 MW Gigawatt Park gas-fired power station, in Ressano Garcia.

The project, which took 18 months to complete, was developed by South African investment group and majority shareholder in the project Gigajoule International.

CEO Johan de Vos told Engineering News Online that the plant had an installed capacity of about 120 MW. The plant’s 13 generators of 9.3 MW each were manufactured by multinational corporation ABB and powered by Rolls-Royce engines.

Gigawatt chairperson Castigo Langa added that the electricity generated by the power station was supplied to power utility Electricidade de Moçambique under a long-term power purchase agreement, both for use within Mozambique, as well as for sale to the regional Southern African Power Pool network.

“The capacity of this power station represents about 24% of the needs of southern Mozambique, excluding that of the MOZAL aluminium smelter. Without a doubt, this is a noteworthy contribution to reducing the country’s energy deficit,” he said.

Matola Gas Company supplied the natural gas to power the Gigawatt Park plant from a pipeline that branched off the main pipeline from Pande, Mozambique, to South Africa.

About $200-million was invested in developing the project. The turnkey contract was implemented by a consortium comprising engineering firms WBHO and PB Power and solar thermal power company TSK as the main subcontractor.

“Since there is insufficient gas available to sustain a long-term contract of this order of magnitude, we have subcontracted Aggreko to produce energy using power stations that can be dismantled to satisfy short-term commercial agreements of between two and four years,” Castiga noted.

He stated that Gigawatt remained committed to seeking better paths for expanding the capacity of the power station until it reached what was set out in its concession licence.

“The concession that was awarded to Gigawatt was 350 MW and we have secured additional gas to increase the plant’s capacity by another 40 MW,” he said.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

Showroom

VEGA Controls SA (Pty) Ltd
VEGA Controls SA (Pty) Ltd

For over 60 years, VEGA has provided industry-leading products for the measurement of level, density, weight and pressure. As the inventor of the...

VISIT SHOWROOM 
Multotec
Multotec

Multotec, recognised industry leaders in metallurgy and process engineering help mining houses across the world process minerals more efficiently,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.072 0.124s - 137pq - 2rq
Subscribe Now