Mount Peake vanadium/titanium/iron project, Australia
This article has been supplied.
Name and Location
Mount Peake vanadium/titanium/iron project, Northern Territory, Australia.
Client
TNG.
Project Description
The prefeasibility study on the Mount Peake project envisages the construction of a processing plant, with an initial capacity of 2.5-million tons a year, increasing to 5-million tons a year.
The process to be employed involves leaching, followed by the selective recovery of iron and vanadium using the Tivan process.
The proposed plant will be divided into eight major processing areas – crushing, grinding and beneficiation; leaching, titanium beneficiation, solvent extraction, acid regeneration, tailings disposal and vanadium precipitation.
Total metal production is estimated at 245 000 t vanadium, 20.3-million tons of iron and 6.5-million tons of titanium.
Value
The total cost of the project is estimated at A$715-million, including A$563-million for the initial 2.5-million-ton-a-year plant and A$122-million for the expansion to five-million tons a year.
Duration
TNG aims to start construction of the project in 2014, with production and exports proposed to start in 2015.
Latest Developments
TNG has appointed Arccon Mining Services to complete the definitive feasibility study (DFS) for the Mount Peake project.
The DFS will define the key requirements for the project including civil/structural, mechanical and electrical engineering; project implementation, including a master schedule and project procurement, contracting and construction plans; project infrastructure and logistics requirements; as well as capital and operating cost estimates to about 10% accuracy.
The DFS is expected to be completed in the fourth quarter of 2013.
Key Contracts and Suppliers
Arccon Mining Services (DFS) and GHD (environmental-impact study).
On Budget and on Time?
Too early to state.
Contact Details for Project Information
TNG, tel +61 8 9327 0900, fax +61 8 9327 0901 email corporate@tngltd.com.au.
Arccon Mining Services, tel +61 8 9340 6100, fax +61 8 9340 6150 or email mining@arccon.com.au.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation