Marampa Q2 output rises, logistics hamper sales

Marampa mine

Marampa mine

17th July 2014

By: Natasha Odendaal

Creamer Media Senior Deputy Editor

  

Font size: - +

JOHANNESBURG (miningweekly.com) – While London Mining’s Sierra Leone-based Marampa iron-ore mine achieved an increase in output during the quarter ended June 30, logistical challenges hit sales.

The iron-ore explorer on Thursday reported a 30% quarter-on-quarter hike in production to 1.2-million wet metric tonnes (wmt).

However, the group posted a 5% dip in sales to 830 000 t in the quarter under review on the back of transshipment issues, including the floating offshore transhipment platform having cut loading rates in June to allow for maintenance and repairs and a dispute over the transportable moisture limit of 10.9%, which had since been resolved.

While analysts at Liberum Capital believed the logistical challenges could put London Mining’s balance sheet under additional stress in the second half of the year, London Mining said it had moved to rectify and improve the movement of its product ahead of the wet season.

The iron-ore miner increased the loading rate at the barge loading facilities by 25% to a yearly installed capacity of 8.8-million wmt and acquired two new pusher barges, which arrived during the quarter under review.

“[The] significant cost benefits [expected] from the more efficient barging format, which uses less fuel than the two-tug-per-barge solution employed in the first two years of operation and has half the cycle time, will be realised from the third quarter.

“Critical path items are under way to allow loading of larger Capesize vessels in the inner harbour in the first quarter of 2015,” London Mining CEO Graeme Hossie said in a statement.

The group maintained its guidance for the full year of between 4.9-million wmt and 5.4-million wmt as it focused on increasing production rates by between 10% and 20% above current nominal capacity through debottlenecking and plant optimisation.

London Mining would, this month, initiate a low-cost optimisation programme to redirect excess milled high-grade material from the spirals circuit to the magnetic separation plants.

This was expected to allow the plants to consistently operate at 110% to 120% of nominal capacity – the equivalent of 5.9-million wmt to 6.5-million wmt a year, explained Hossie.

Meanwhile, progress had been made with efforts to secure a strategic partner for its Marampa operations to reduce debt and fund an accelerated growth plan on the back of ongoing pricing volatility.

Following the decline of the iron-ore price, exacerbated by an uncertain price environment, London Mining had been managing its cash flow “tightly”, while working to increase its financial headroom.

A new $17.5-million facility had been arranged and drawn down from Vitol as a partial prepayment on 500 000 t of future unallocated exports.

Further, active and constructive discussions were ongoing with its lending banks for an additional short-term working capital tranche of up to $25-million, maturing towards the end of 2014.

The combination of these two measures would satisfy expected short-term liquidity and headroom requirements under current conditions.

Liberum noted that the short-term debt funding would see the iron-ore miner through to concluding a deal with a strategic partner, which could “revolutionise” the company’s balance sheet and short-term prospects.

Edited by Chanel de Bruyn
Creamer Media Online Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Axiom Hydraulics
Axiom Hydraulics

Axiom Hydraulics is a trusted leader in South Africa’s hydraulic industry, delivering world-class components, systems, and engineering expertise...

VISIT SHOWROOM 
Egoli Gas (Pty) Ltd
Egoli Gas (Pty) Ltd

As a reticulator, Egoli Gas provides natural gas to homes and businesses via underground pipes.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.079 0.861s - 140pq - 2rq
Subscribe Now