https://www.engineeringnews.co.za

Main power line infrastructure at SA diamond mine completed

16th August 2013

By: Natasha Odendaal

Creamer Media Senior Deputy Editor

  

Font size: - +

The final key infrastructure at TSX-listed Diamcor Mining’s Krone-Endora at Venetia project, in South Africa, has been completed with the installation of an 8.4 km main power supply line.

The power line, constructed by State- owned power utility Eskom, will replace the diesel generators currently being used at the project and will provide immediate operational cost savings and reduced downtime.

The emerging rough diamonds producer installed an additional 700 m power line to support the in-field screening plant.

The diesel generators will now provide standby power at both the main plant and the in-field screening plant.

“The installation of the main power line to the project marks the successful completion of the final infrastructure item for the project and one that will provide imme- diate benefits for operating costs and reli- ability,” said Diamcor president and CEO Dean Taylor.

He added that a crushing circuit at the main plant was currently being installed. Once complete, it was expected that the circuit would increase the processing of larger-size fractions and provide additional opportunities for the recovery of larger diamonds.

The group recovered four additional ‘special’ diamonds of 12.82 ct, 17.75 ct, 20.48 ct and 48.26 ct during the ongoing testing and commissioning work.

This followed the May recovery of the first 11.23 ct special diamond during initial testing of material in the 1-mm-to-10-mm-size fraction, and the July recovery of two additional special diamonds of 13.38 ct and 15.16 ct during the early processing of material in the 12-mm-to-28-mm-size fraction.

Diamcor has, to date, recovered and tendered a total of 6 702.9 ct of diamonds for total gross proceeds of $926 324.03 from the initial testing and commissioning exercises.

The company had also delivered 3 460 ct of diamonds for tender and sale in the coming weeks.

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

MBE Minerals SA (Pty) Ltd
MBE Minerals SA (Pty) Ltd

Your global lifecycle technology & service partner for materials & minerals processing equipment for coal, iron ore, copper, manganese & other...

VISIT SHOWROOM 
Alcohol Breathalysers
Alcohol Breathalysers

Supplier & Distributor of the Widest Range of Accurate & Easy-to-Use Alcohol Breathalysers

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.053 0.693s - 122pq - 2rq
Subscribe Now