Equinox Gold completes Phase 1 construction at Castle Mountain

17th September 2020

By: Creamer Media Reporter

     

Font size: - +

Construction of Phase 1 at the Castle Mountain gold mine, in California, is complete and the first gold pour is expected in the fourth quarter, dual-listed Equinox Gold reported on Thursday.

Equinox started preproduction mining in early June and has stacked more than 1.4-million tonnes of ore on the leach pad to date. Commissioning of the plant is in the final stages and irrigation of the leach pad started this week.

Loaded carbon from Castle Mountain will be processed in the carbon stripping and smelting plant at the company's Mesquite mine, also in California.

"Castle Mountain will be Equinox Gold's seventh producing gold mine in the Americas and our second operating mine in California. We expect Castle Mountain to be a long-life flagship asset for Equinox Gold,” said Equinox CEO Christian Milau.

The Castle Mountain Phase 1 mine will process 12 700 t/d of ore, producing an average of 45 000 oz/y.

The company is completing a feasibility study for the potential Phase 2 expansion, which is expected to average 200 000 oz/y.

Edited by Mariaan Webb
Creamer Media Senior Deputy Editor Online

Comments

Showroom

SAIMC (Society for Automation, Instrumentation, Mechatronics and Control)
SAIMC (Society for Automation, Instrumentation, Mechatronics and Control)

Education: Consulting with member companies to obtain the optimal benefits from their B-BBEE spending, skills resources as well as B-BBEE points

VISIT SHOWROOM 
SABAT
SABAT

From batteries for boats and jet skis, to batteries for cars and quad bikes, SABAT Batteries has positioned itself as the lifestyle battery of...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (12/04/2024)
12th April 2024 By: Martin Creamer
Magazine round up | 12 April 2024
Magazine round up | 12 April 2024
12th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.082 0.139s - 158pq - 2rq
Subscribe Now