DRDGOLD temporarily suspends new flotation and fine-grind circuits
DRDGOLD announced today that it has temporarily suspended its recently constructed high grade section – a flotation circuit, a set of fine-grind mills and the cyanide leach and carbon in pulp circuit – to determine the cause of the metallurgical problems that have led to lower than expected gold production for Q3 FY14.
Although the new FFG technology, introduced to liberate more gold and increase recoveries by between 16% to 20%, has achieved positive float and grinding results, the CIP section has not yet stabilised and appears to have also contributed to metallurgical instability and carbon inefficiencies downstream in the existing carbon in leach circuit or low grade section. Suspending the new section will enable the operational team to stabilise the low grade circuit and to determine the factors that could be affecting carbon efficiencies in both circuits. The company expects the original lower-grade CIL circuit to be settled within a month. The subsequent test work is likely to be completed within a further three to four month period. Incessant rains during February and March and surges, dips and interruptions in the power supply during this period have also negatively impacted both the high grade and low grade sections, contributing to the metallurgical instability of both sections.
The Ergo team will therefore make use of the down-time to install drain valves to prevent silting up of the float cells during future power fluctuations, and auxiliary power units to thickener underflow pumps to prevent silting up of thickeners during these trip-outs. The FFG and high grade CIP circuit came into full operation in mid-January 2014 following the commissioning of a third thickener. Initial results were positive and utilisation was generally good.
Flotation
efficiencies and the performance of the fine-grind mills were consistent with targets. Sampling results show that the amount of gold remaining in solids (the so-called “washed residue grade”) reduced to within target range. This suggested the gold that previously remained inert within the pyrites was now driven off and had become soluble. However, loaded carbon values remained well below the target range in both the CIP and CIL circuits. This indicated that the gold remained in solution and was not being adsorbed onto carbon. To some extent this may be attributable to poor carbon efficiency – caused by volatile density levels in the feed at various stages in the process – which in turn is attributed to the thickeners that manage the flow of feed into the main CIL section. It may also be a knock-on effect of the reagents used in the flotation cells.
Currently both carbon circuits of the plant – the higher grade CIP and the lower grade CIL – are unstable and are operating well below target range.
As a result of these metallurgical inefficiencies and the resultant high dissolved gold losses, gold production for the quarter ended March 2014 is estimated to be 14% lower compared to the preceding quarter, and all-in sustaining unit costs are estimated to be up by 24% quarter on quarter.
Because of a higher gold price and lower total operational and capital expenditure, the company’s cash balance remained virtually unchanged quarter on quarter.
A basic summary of the FFG process and its interaction with the low grade CIL circuit is provided for reference:
Slurry is sourced from various reclamation sites and is delivered to Ergo’s Brakpan plant. The slurry, or feed, is pumped through three banks of flotation cells to create a concentrate that contains gold-bearing pyrites. The concentrate enters a set of fine-grind mills to break down the pyrites and release gold which would otherwise have remained shielded from the subsequent metallurgical extraction process. (Gold trapped in these pyrites is the main target of the FFG and the reason for its construction.) This fine pulp then enters a high grade leach circuit, where cyanide is added to dissolve the gold in the pulp. The concentrate is then pumped to the CIP section where activated carbon is added and the dissolved gold is adsorbed. This loaded carbon is processed through an elution circuit, where the gold is stripped off the carbon into solution. This solution then flows through a series of electro-winning cells where the gold is electrically deposited onto electrodes. Periodically the gold is washed off the electrodes, calcined and smelted into doré bars.
The remaining 96% of the feed leaves the flotation circuit and enters the low grade circuit. It first enters a set of three thickeners to increase its density before being pumped into the main CIL tanks. It is essential that the thickeners are in good working order and stable, because the high grade tail cannot be processed by the low grade circuit until it has been thickened. Their purpose is therefore to increase the density of the feed, otherwise the carbon that is introduced later in the process will sink to the bottom of the CIL tanks, and not remain in suspension. From this point onwards in the low grade CIL circuit, the feed is subjected to a similar process to the one described above – cyanidation, carbon loading, elution, electro-wining and finally smelting into doré bars.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation