Choczewo nuclear power plant project, Poland – update

Image of nuclear power plant design plans

3rd April 2026

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Choczewo nuclear power plant (NPP) project.

Location
Lubiatowo-Kopalino site, in the Choczewo municipality of Pomerania, in Poland.

Project Owner/s
State-owned Polskie Elektrownie Jądrowe (PEJ).

Project Description
Choczewo will comprise three AP1000 nuclear units and will be the first nuclear project in Poland.

Potential Job Creation
Not stated.

Capital Expenditure
Not stated.

Planned Start/End Date
Construction of each reactor is expected to take about seven years, followed by about one year of testing and commissioning. The first reactor will begin commercial operation in 2036, the second in 2037 and the third in 2038.

Latest Developments
PEJ reported on March 31 that it had applied for a construction licence to build the NPP.

The document submitted by PEJ is the investor’s formal application filed with the PAA President in accordance with the requirements specified in the Atomic Law Act. The entire documentation comprises more than 40 000 pages. The application was prepared by more than 200 experts from various areas, primarily nuclear safety and radiological protection.

The documents included in the application confirm compliance with the requirements of nuclear safety, radiological protection and security, as well as the investor’s ability to deliver the project.

One of the key documents submitted with the licence application is the Preliminary Safety Analysis Report. This report is one of the most important appendices, providing a detailed description of the power plant design and the project site. It also includes comprehensive analyses of technical and environmental factors demonstrating that the proposed solutions meet all requirements pertaining to nuclear safety, physical security, radiological protection and nuclear material safeguards applicable to facilities of this type.

The application includes a quality assurance programme, a security classification, a design of a physical security system for a nuclear facility and nuclear materials, basic information on the radiological emergency management system and organisational documentation confirming that the investor has the necessary technical, human and organisational resources to deliver the project.

The PAA president issues a construction licence for a nuclear facility within 24 months of the submission of the application, excluding the time required for the applicant to submit any additional documentation, if necessary. 

Construction is expected to start in the fourth quarter of 2028, starting with the pouring of the first nuclear concrete. To start construction work in accordance with this schedule, the investor must have a construction licence from the PAA president and a construction permit issued by the Head of the Pomorskie Voivodeship. 

PEJ plans to submit the construction permit application in 2027.

Key Contracts, Suppliers and Consultants
Westinghouse and Bechtel consortium (NPP construction).

Contact Details for Project Information
PEJ, tel +48 22 340 2980 or email komunikacja@ppej.pl.
 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Environmental Impact Management Services
Environmental Impact Management Services

EIMS is an independent specialised environmental consulting firm offering the full spectrum of environmental management services across all sectors...

VISIT SHOWROOM 
Craig Miller Technical Services (CMTS)
Craig Miller Technical Services (CMTS)

CMTS is a leading, well-established EC&I contractor with 37+ years of mining and industrial experience. We execute full-scope EC&I projects with...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.114 0.97s - 213pq - 2rq
Subscribe Now