TORONTO (miningweekly.com) – West Africa-focused project developer Asanko Gold has awarded the mining contract for the fully funded and permitted $295-million first phase of the Asanko gold mine, in Ghana.

Project construction started in August and had been advancing rapidly with the project on schedule and within budget. Phase 1 was expected to produce 200 000 oz/y of gold at a steady state, starting from the second quarter of 2016, with the first gold pour planned for the first quarter of that year.

The main mineral resource for Phase 1 is the Nkran pit, immediately next to the new plant site currently under construction. The pit was previously mined to a depth of about 120 m and required 21.7-million tonnes of waste to be prestripped before ore mining could start by the end of next year.

Asanko reported on Wednesday that it had awarded the mining contract for the Nkran prestrip and the first year of mining operations to PW Ghana, a subsidiary of PW Mining International of Accra, after a rigorous tendering process.

PW’s extensive experience in West Africa and a full fleet of equipment in excellent condition that could be immediately deployed to the project site counted in its favour. Prestripping was expected to start in January, with mobilisation, clearing and grubbing starting immediately.

The process of finding a mining contractor started in May, when Asanko invited 19 mining contract companies to tender. From these initial submissions, it was determined that a shortlist of seven companies had the capability to meet the project timelines and quantities. In July, these shortlisted companies were invited to provide a more detailed tender. Four of the tenders submitted were selected for a detailed technical and commercial review.

An independent quantity-survey company was then used to provide the commercial adjudication and a panel of Asanko's Ghanaian mining team conducted technical adjudications. In the adjudication process, the bids were evaluated based on the contractor's observed expertise and performance in safety, training, equipment availability, maintenance and operating excellence.

Asanko also gave significant weighting to local ownership of the tendering companies, in keeping with the mandate of the African Union’s Mining Vision.

Edited by Tracy Klückow
Creamer Media Contributing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Hanna Instruments (Pty) Ltd
Hanna Instruments (Pty) Ltd

We supply customers with practical affordable solutions for their testing needs. Our products include benchtop, portable, in-line process control...

VISIT SHOWROOM 
Craig Miller Technical Services (CMTS)
Craig Miller Technical Services (CMTS)

CMTS is a leading, well-established EC&I contractor with 37+ years of mining and industrial experience. We execute full-scope EC&I projects with...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.053 1.203s - 140pq - 2rq
Subscribe Now