Name of the Project
Zanaga iron-ore project.

Location
The Zanaga project is located 30 km west of Zanaga, a regional centre of the Lekoumou department of the Republic of Congo.

Client
The project is a joint venture (JV) between Glencore (50% plus one share) and the Zanaga Iron Ore Company (ZIOC).

Project Description
The project has probable ore reserves of 2.5-billion tons grading at 34% iron. A feasibility study completed on the project envisages a multistage development of the mine.

Stage 1 involves development to an initial 12-million tonnes a year of high-quality iron-ore product, while Stage 2 will entail an 18-million-tonne-a-year expansion to 30-million tonnes a year of total product.

Stage 1 has been designed as a standalone business case and does not rely on or require the Stage 2 expansion. The Stage 1 operation will mine the higher-grade upper hematite ores over a 30-year mine life, producing a 66% iron content and a premium-quality iron-ore pellet feed product with low impurities.

The initial openpit mining operation will use contractor mining to exploit free-dig material with a very low strip ratio, with simpler processing requirements resulting in low initial power demand. The ore will be upgraded into a high-grade pellet feed using conventional gravity and flotation concentration methods before being pumped to the port through a slurry pipeline. The project's onshore port facilities and infrastructure will include a filter plant to dewater the concentrate, and a covered ore-storage facility, located at a proposed new third-party port that will be built 9 km north of the existing Port of Pointe-Noire.

Stage 2 will involve openpit mining of the magnetite orebody. The strip ratio will be lower than that of Stage 1, as the upper hematite cap will have been mined. The processing plant will be expanded, with a second concentrator using magnetic separation to produce a blended 67.5% iron content, premium-quality iron-ore pellet feed product. The increased power requirements will be supplied by planned power generation expansion projects in RoC. A second slurry pipeline will be constructed to transport the ore to port, where the port facilities will be expanded as part of the proposed deep-water port development.

The staged development approach adopted by Glencore in the feasibility study has demonstrated significant advantages over the prefeasibility study announced in November 2012, which considered a single-stage 30-million-tonne-a-year development at a capital cost of $7.5-billion.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
Not stated.

Value
Stage 1 is expected to cost $2.2-billion, including contingency, and Stage 2 $2.5-billion.

The first-stage operation could potentially finance the second-stage expansion through project cash flows, limiting the level of additional equity required for the operation.

Duration
Front-end engineering and design is expected to start in early 2015.

Latest Developments
ZIOC expects the environmental permit for Zanaga from the RoC’s Ministry of Environment to help attract finance to allow for the valuable resource to be brought into production.

The project was awarded the permit for the first phase of development in November 2017.

The first phase remains dependent on financing, although it is encouraged by improving iron-ore market conditions for premium products.

Staged development is beneficial to the Zanaga project, as it lowers capital and execution risk, reduces financing requirements and increases return on capital investment, the ZIOC has stated.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
DRA (process plant study).

Contact Details for Project Information
ZIOC corporate development and investor relations manager Andrew Trahar, tel +44 20 7399 1105 or email info@zanagairon.com.
DRA, tel +27 11 202 8600 or email info@DRAglobal.com.
 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

EKATO Africa
EKATO Africa

Established in 1933, EKATO is the world leader in agitation technology, supplying agitators for processes and applications such as chemicals and...

VISIT SHOWROOM 
Multotec
Multotec

Multotec, recognised industry leaders in metallurgy and process engineering help mining houses across the world process minerals more efficiently,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.052 1.312s - 149pq - 2rq
Subscribe Now