https://www.engineeringnews.co.za
Construction|Contractor|Design|Environment|PROJECT|Projects|System|Transnet|Solutions
Construction|Contractor|Design|Environment|PROJECT|Projects|System|Transnet|Solutions
construction|contractor|design|environment|project|projects|system|transnet|solutions

World-class projects in SA are being rolled out with the NEC4 contract. Are you up-to-speed?

24th May 2019

By: Creamer Media Reporter

     

Font size: - +

This article has been supplied as a media statement and is not written by Creamer Media. It may be available only for a limited time on this website.

Described by the NEC as an ‘evolution, not a revolution’, the NEC4 builds on the success as well as the content of the NEC3 to achieve further improvements.  Alusani® Course Leader, Cameron Staude, says that most of South Africa’s state-owned enterprises, including Transnet and Eskom, are predominantly rolling out contracts based on the NEC3 suite of contracts.

“While the Construction Industry Development Board’s regulations haven’t been updated since 2015, they do prescribe that the latest contract be used. Currently, the latest contracts that are at our disposal are FIDIC 2017, JBCC 6.2, GCC 2015, and NEC4,” says Staude.

This makes it essential for professionals in the built environment to quickly get up to speed on all its new features.

“The project team involved in the R4.4-billion MeerKAT radio telescope project, which will eventually become part of the Square Kilometre Array, is leaning towards using the NEC4 contract suite.  The progressive nature of the contract, combined with its appeal on large projects where there are international stakeholders, made NEC4 the contract of choice,” says Staude.

Many of the new features of the NEC4 contract allow for greater flexibility. There are also two new forms of contract, namely the NEC4 Design, Build and Operate Contract (DBO) and the NEC4 Alliance Contract (ALC), providing an even greater range of potential contract and procurement solutions for clients who are undertaking projects and works programmes.

“One of the interesting features in NEC4 is a clearly stipulated process for the Early Warning system, which is a mechanism where the Project Manager or Contractor notifies relevant parties of a potential risk before they occur so that the parties can avoid or mitigate the risk. In NEC3, there was uncertainty about the steps that the Project Manager had to take if a potential risk was picked up, but NEC4 gives clear guidance on how these situations should be handled,” says Staude.

NEC4 stipulates that the Project Manager prepares the first Early Warning Register and issues it to the Contractor within one week of the starting date.  The Project Manager instructs the Contractor to attend the first early warning meeting within two weeks of the starting date.  Later early warning meetings are held if either the Project Manager or the Contractor instructs the other to attend and at any case at no longer intervals than the intervals stated in the Contract Data until Completion of the whole of the works.

“The NEC4 encourages a collaborated approach, instead of a regimented one. The way that the processes have been clearly defined ensures that there is a regular commercial management process for the project, which will benefit all parties involved,” says Staude.

The NEC4 also provides two incentives for the Contractor which didn’t exist under pricing Options A and B of NEC3.  NEC4 has introduced a Contractor’s Proposal where it can make proposals to reduce the Employer’s Prices whilst sharing in a pre-agreed percentage of the sharing as well as a proposal for acceleration to reduce the Completion Date. Further the NEC4 now provides for a final payment certificate as well as a new dispute resolution process where disputes are hopefully avoided.

“Regardless the size or type of project, the NEC4 contract can work for you. I’m here to give you the practical advice you need on how to effectively make the transition from NEC3 to NEC4,” concludes Staude.

Edited by Creamer Media Reporter

Comments

Showroom

Environmental Assurance (Pty) Ltd.
Environmental Assurance (Pty) Ltd.

ENVASS is a customer and solutions-driven environmental consultancy with established divisions, serviced by highly qualified and experienced...

VISIT SHOWROOM 
Schauenburg SmartMine IoT
Schauenburg SmartMine IoT

SmartMine IoT has been developed with the mining industry in mind, to provides our customers with powerful business intelligence and data modelling...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 19 April 2024
Magazine round up | 19 April 2024
19th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.075 0.13s - 162pq - 2rq
Subscribe Now