https://www.engineeringnews.co.za

Woodlawn zinc/copper project, Australia

15th September 2017

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Woodlawn zinc/copper project.

Location
New South Wales, Australia.

Client
Heron Resources.

Project Description
A feasibility study on the Woodlawn project supports the viability of a starter case to deliver zinc, copper and lead concentrates to the market over a significant reserves-based mine life. The project has total underground mineral reserves of 2.8-million tonnes grading 14% zinc equivalent, 5.5% zinc, 1.6% copper, 1.9% lead, 0.45 g/t gold and 42 g/t silver. Reclaimed tailings mineral reserves are estimated at 9.5-million tonnes grading 6% zinc equivalent, 2.2% zinc, 0.5% copper, 1.3% lead, 0.31 g/t of gold and 31 g/t silver.

An initial 9.3-year mine life, based on processing the combined underground and tailings mineral reserves, is expected. Inferred mineral resources defined in the underground and tailings projects demonstrate excellent potential to extend the mine life to more than 11.5 years.

The underground mine plan focuses on the shallower areas of the deposit, reflecting the success of the preliminary economic assessment completed in 2015 and feasibility study drilling programmes.

The underground deposit will be accessed through a boxcut located to the west of the existing openpit, allowing for the early development of shallow underground material. Stoping areas will be accessed predominantly through a new decline and new access drives; however, in some areas, the existing workings are planned to be rehabilitated and used.

The mine access drives range from 3 m × 3 m to 5.5 m × 5.5 m, with gradients of up to 1:7, depending on the intended use. Overall mine layout is consistent with standard practice in Australian underground mines reliant on decline access and vertical excavations for ventilation returns, and a second means of egress (escape way).

Mining of the reclaimed tailings ore will be undertaken using automated monitor-based hydraulic mining, which uses a high-pressure water cannon to agitate the ore into a slurry. In consultation with hydraulic mining consultants, the mining approach has been revised from a top-down to a bottom-up mining method, which is considered to be safer, with lower environmental impacts, as well as being easier to control and more cost effective.

The study envisages a processing rate of up to one-million tonnes a year from underground mining and up to 1.5-million tonnes a year from reclaimed tailings processed through a standard single-sulphide flotation facility.

For underground ore, a two-stage crushing circuit has been incorporated into the plant design, together with a primary ball mill.

For reclaimed tailings ore, a fine-grind mill is to be installed to reduce the particle size to 30 μm, a size that previous and current testwork has confirmed maximises recovery performance from the flotation circuit.

For the underground ore, the initial float (copper concentrate) is undertaken at 75 μm, with a regrind of copper tails to 30 μm to maximise the subsequent recoveries from the lead and zinc flotation stages.

The flotation circuit comprises a gangue-prefloat, copper, lead and zinc differential flotation sequence.

The overall plant design is broadly consistent with the design of the original plant used from 1978 to 1998 to successfully treat Woodlawn ore.

Cleaner concentrate recovered from the prefloat flotation cleaner cell will be discarded to final tails to remove the silicate gangue before it reaches the differential base metal flotation circuit. A differential flotation circuit for copper, lead and zinc will be used, with concentrate regrind stages in the copper, lead and zinc circuits to produce cleaner concentrates. The copper circuit will also use a rougher and scavenger tailings regrind circuit prior to the lead flotation stage.

Concentrates from the copper, lead and zinc flotation circuits will be thickened and subsequently filtered for road transport.

The project is expected to produce 40 000 t/y of zinc, 10 000 t/y of copper and 12 000 t/y of lead at steady state, contained in zinc, copper and lead concentrates.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has a post-tax net present value, at an 8% discount rate, of A$207-million and an internal rate of return of 32%, with a payback of 2.3 years.

Value
Initial capital costs of A$144.2-million have been estimated.

Duration
The aim is to bring the project into production in 2018.

Latest Developments
Woodlawn is now fully funded from construction to ramp-up.

Heron Resources has completed a A$141-million equity funding package, as part of its greater A$240-million funding to develop the Woodlawn zinc/copper project, in New South Wales.

The equity funding includes a A$104-million cornerstone investor placement to Greenstone Resources and co-investors Orion Mine Finance Group and Castlelake LP, as well as a A$32-million institutional placement.

The equity funding package also includes a A$5-million share purchase plan, of which about A$3.48-million has been subscribed for by existing shareholders. The shortfall balance has been placed to various investors.

The outstanding component of the greater A$240-million raising includes a $60-million senior debt facility and a $16-million prepayment facility, both of which are being provided by Orion.

Heron is working through the remaining conditions precedent on these facilities, including the establishment of underground mining and port facility contracts, and an independent engineers report.

At steady state, Woodlawn is expected to produce 70 000 t/y of zinc concentrates, 30 000 t/y of copper concentrates and 25 000 t/y of lead concentrates.

Key Contracts and Suppliers
Ertech (earthworks contract).

On Budget and on Time?
Too early to state.

Contact Details for Project Information
Heron Resources, tel +61 2 9119 8111 or email heron@heronresources.com.au.
 
 
 
 
 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

ABB Electrification
ABB Electrification

Electrifying the world in a safe, smart, and sustainable way, ABB Electrification is a global technology leader in electrical distribution and...

VISIT SHOWROOM 
EKATO Africa
EKATO Africa

Established in 1933, EKATO is the world leader in agitation technology, supplying agitators for processes and applications such as chemicals and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.045 0.864s - 127pq - 2rq
Subscribe Now