Westermeerwind wind farm project, the Netherlands
Name and Location
Westermeerwind wind farm project, the Netherlands.
Client
Westermeerwind.
Project Description
The project involves the construction of the Netherlands’ largest near-shore wind farm.
The 144 MW wind farm will be erected in Ijsselmeer lake, along the northern and western dyke of the Noord-oostpolder municipality.
Forty-eight wind turbines will be arranged in three rows in the shallow waters between 500 m and 1 100 m from the dyke.
Each of these direct-drive wind turbines will generate an output of 3 MW, with 108 m rotor diameters ensuring maximum efficiency.
Value
The project will cost more than €400-million to implement.
Duration
Commissioning of the wind farm is expected between the end of 2015 and early 2016.
Latest Developments
Siemens Energy has been awarded a turnkey contract for its gearless technology for the near-shore project. Siemens will supply 48 of its SWT-3.0-108 wind turbines.
Key Contracts and Suppliers
Siemens Energy (turnkey wind farm contract), Ballast Nedam and Mammoet (foundations and installation of the windmills), Visser & Smit Marine Contracting (cabling to the electrical substation) and Ventolines (project management).
On Budget and on Time?
Not stated.
Contact Details for Project Information
Westermeerwind, tel +31 527 61 61 67 or email info@westermeerwind.nl.
Siemens Energy, Bernd Eilitz, tel +49 40 2889 8842 or email bernd.eilitz@siemens.com.
Ballast Nedam, tel +31 30 285 33 33 or email pr@ballast-nedam.nl.
Mammoet, tel +31102042424,
fax +31102042442 or
email info@mammoet.com.
Visser & Smit Marine Contracting,
tel +31 78 641 7500 or fax +31 78 641 7501.
Ventolines, tel +31 527 616167 or
email info@ventolines.nl.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation