West Musgrave base metals project, Australia – update
Name of the Project
West Musgrave base metals project.
Location
West Musgrave Ranges of Western Australia.
Project Owner/s
Copper/gold miner OZ Minerals.
Project Description
The West Musgrave includes the Nebo-Babel nickel/copper and Succoth copper deposits.
OZ Minerals is hoping to establish the West Musgrave project as a scaleable, low-cost, long-life, openpit mining operation.
An updated prefeasibility study (PFS) has increased the project’s mineral ore reserves from 220-million tonnes grading 0.36% copper and 0.33% nickel, to 253-million tonnes grading 0.35% copper and 0.32% nickel.
Mineral resources have increased – from 340-million tonnes grading 0.36% copper and 0.33% nickel in the February 2020 PFS to 390-million tonnes grading 0.34% copper and 0.31% nickel in the updated PFS.
The updated PFS envisages a 12-million-tonne-a-year crushing, vertical roller mill, flotation operation producing separate copper and nickel concentrates. The average nickel production from the project has increased from 22 000 t/y in the February 2020 PFS to 26 000 t/y in the updated PFS. Average copper production has increased from 28 000 t/y to 32 000 t/y.
Potential Job Creation
Not stated.
Net Present Value/Internal Rate of Return
The updated PFS has increased the project’s after-tax net present value from A$800-million to A$1-billion, and the internal rate of return from 20% to 25%, with a payback of about six years from the decision to mine.
Capital Expenditure
Preproduction capital has increased from A$995-million in the February 2020 PFS to about A$1.1-billion in the February 2021 updated PFS.
Planned Start/End Date
Not stated.
Latest Developments
The Western Australian government has granted copper miner OZ Minerals the third and final regulatory approval for its West Musgrave project.
Discussions are well advanced with the Ngaanyatjarra Council on finalising the mining agreement with significant progress made over the past several months.
The project is on track for a final investment decision during this final half of the year.
In addition to completion of the mining agreement with representatives of the traditional owners, the team is finalising various study components and continuing to assess the impact of cost inflation and the operational environment on project cost and schedule.
West Musgrave is nearing completion of the study phase.
Key Contracts, Suppliers and Consultants
Not stated.
Contact Details for Project Information
OZ Minerals, tel +61 8 8229 6600 or email info@ozminerals.com.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation