Wesizwe resumes construction activities at Bakubung, but funding shortage a challenge

18th March 2022

By: Creamer Media Reporter

     

Font size: - +

Although construction resumed at Wesizwe's Bakubung mine in mid-February, the mine is now behind its construction schedule.

Wesizwe on February 8 informed shareholders that community protests had interrupted the development of its Bakubung mine and that construction of the mine had been halted for the safety of employees.

Wesizwe says that although an agreement has not yet been reached with the community, Bakubung Platinum Mine is engaging with the community to find a solution and that construction has, therefore, resumed.

However, the company did not complete the construction of the Phase 1 concentrate processing plant during December 2021 as planned. Some of the underground construction projects have also been delayed.

As Bakubung Platinum Mine has not achieved operational status, it therefore has no operating income while still being contractually obliged to repay the principal and interest of its loan as it comes due and thus needs additional funds.

"The impact of the Covid-19 pandemic, community protests and funding shortage has aggravated the mine’s already delayed project construction schedule.

"Management is reviewing the new construction schedule and will communicate it in the Integrated Annual Report 2022. Wesizwe management is doing its best to overcome difficulties to ensure that construction progresses and to solve the shortfall funding issue," the company reports.

Edited by Chanel de Bruyn
Creamer Media Online Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

AutoX
AutoX

We are dedicated to business excellence and innovation.

VISIT SHOWROOM 
Egoli Gas (Pty) Ltd
Egoli Gas (Pty) Ltd

As a reticulator, Egoli Gas provides natural gas to homes and businesses via underground pipes.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.071 0.945s - 140pq - 2rq
Subscribe Now