Tulu Kapi gold project, Ethiopia
Name and Location
Tulu Kapi gold project, Ethiopia.
Client
Kefi Minerals.
Project Description
Tulu Kapi has a total resource estimated at 24.1-million tonnes at 2.64g/t of gold, containing 2.05-million ounces.
A scoping level review of the Tulu Kapi project, acquired by Kefi in December 2013, indicates potential for further improvement in the economic performance of the project.
The review has confirmed that the targeted openpit mine production for the project can be increased to 1.2-million ounces a year, as opposed to the company’s preacquisition estimate of 800 000 oz/y.
Value
Capital expenditure is estimated at $143-million.
Duration
The definitive feasibility study (DFS) is planned to be completed in late 2014, with construction scheduled to start in 2015.
Latest Developments
The revised Tulu Kapi mine plan has been developed, which reflects Kefi’s selective mining approach.
This mine plan will be further refined within the scheduled DFS, which will be conducted later this year, following the completion of Kefi’s current drilling and trenching programme.
The mine plan will then be integrated into a refined DFS that will take into account Kefi’s metallurgical testing, engineering, cost verification and economic optimisation.
As Kefi continues to refine the selective mining techniques, it expects to report further improvements during the following months and to reactivate the mining licence application by the end of this year. As a result, the company remains confident of fulfilling its commitment to the Ethiopian government that production will start in 2016.
Key Contracts and Suppliers
None stated.
On Budget and on Time?
Not stated.
Contact Details for Project Information
Kefi Minerals, tel +90 232 381 9431, fax + 90 232 381 9071 or email info@kefi-minerals.com.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation