Toyota South Africa Motors investment programme, South Africa

3rd April 2020

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Toyota South Africa Motors (TSAM) investment programme.

Location
Prospecton, in KwaZulu-Natal, and Gauteng, South Africa.

Project Owner/s
TSAM.

Project Description
TSAM plans to invest R4.28-billion in its local operations until the end of 2020.

The investment will straddle several areas of the local company’s operations.

Most of the investment has been allocated to prepare for the production of a new passenger-car model at the Prospecton plant. The new vehicle will replace the Corolla production line, which is due to come to an end this year. The new vehicle will include a Toyota hybrid synergy drive model. The production of the Corolla Quest will continue.

Other investments include upgrades to the local production of the Hiace Ses’fikile mini bus, as well as an increase in production volume of this model from 14 000 to 18 000.

A packing plant will also be established to support knock-down production of the Hilux bakkie in Kenya.

TSAM also plans to double the size of its Atlas warehouse, in Gauteng, from 40 000 m2 to 80 000 m2. When completed, the facility will be the largest automotive parts warehouse in the southern hemisphere.

The carmaker also has a number of ongoing projects, which include investment in the production of the new Corolla Quest model and several facilities upgrades at the plant.

Potential Job Creation
The proposed production of the new passenger-car is expected to create about 1 500 jobs, of which 500 will be at TSAM and 1 000 with suppliers.                                                                

Upgrades to the local production of the Hiace Ses’fikile mini bus is expected to create 270 new jobs.

Capital Expenditure
Preparations for the production of the new passenger-car model at the Prospecton plant are expected to cost an estimated R2.43-billion.

Upgrades to the local production of the Hiace Ses’fikile mini bus are expected to cost about R454-million to implement. A further R91-million will be spent to increase production from 14 000 to 18 000 units a year and R20-million to establish the packing plant.

The construction of the warehouse is expected to cost about R365-million.

About R18-million will be invested in the production of the new Corolla Quest and R928-million for facilities upgrades.

Planned Start/End Date
The production of the proposed new passenger-car model at the Prospecton plant is expected to start in October 2021.

The packing plant is expected to be completed in 2021.

The investment in the new Corolla quest and upgrades at the plant are expected to be completed this year.

Latest Developments
None stated.

Key Contracts and Suppliers
None stated.

Contact Details for Project Information
TSAM, tel +27 11 809 9111.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

Showroom

Schauenburg SmartMine IoT
Schauenburg SmartMine IoT

SmartMine IoT has been developed with the mining industry in mind, to provides our customers with powerful business intelligence and data modelling...

VISIT SHOWROOM 
SABAT
SABAT

From batteries for boats and jet skis, to batteries for cars and quad bikes, SABAT Batteries has positioned itself as the lifestyle battery of...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 19 April 2024
Magazine round up | 19 April 2024
19th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.084 0.157s - 163pq - 2rq
Subscribe Now