Transnet approaching the courts over controversial contracts to procure 1064 locomotives

9th March 2021

By: News24Wire

  

Font size: - +

Transnet officials have worked until midnight to finalise a review application on the controversial contracts related to the procurement of 1064 locomotives, members of Parliament heard.

The Standing Committee on Public Accounts (Scopa) on Tuesday was briefed by Transnet officials, including group CEO Portia Derby, board chairperson Popo Molefe and Public Enterprises Minister Pravin Gordhan on efforts to improve governance at the entity.

In particular the 1064 locomotives contracts – dating to 2014 - came under the spotlight. The matter has been a subject of investigation by the judicial commission of inquiry into state capture. Costs of contracts ballooned by 41% from R38.6-billion to R54.4-billion. Officials had previously announced intentions to approach the courts to recover monies lost to companies who did no work.

Gordhan told members of Scopa that there is a continued effort to recover funds lost through procurement during the state capture era. He said a review application will come before the high court relating to the 1064 locomotives.

Molefe similarly indicated that the review is being filed this morning.

"[It] is a complex contract which disadvantaged Transnet in many respects," said Molefe. He added that it bedevilled the work of freight rail – a "critical component" in revenue generation for the state-owned entity.

"We finished at midnight last night dealing with this application."

Gordhan said that the current board and management are in the process of repositioning and redirecting the business to ensure Transnet is a major logistics provider and to support the economic reconstruction and recovery plan through the provision of logistics.

Chief financial officer Nonkululeko Dlamini gave an overview of steps being taken to improve compliance with the public finance management act, including that contracts are being reviewed to as far back as 2011 to ensure compliance. As a result reported irregular expenditure has been ballooning – as it takes into account historical effects. For example as at 2017/18 reported irregular expenditure was R8.1-billion, by 2019 /20 this escalated to R114-billion.

Gordhan suggested to the committee that non-compliance linked to the state capture period be ringfenced from current data when it comes to reporting.

"History is being pulled into the current period, [which is why] we see large numbers in terms of irregular expenditure," he said. "The past keeps contaminating the evidence of the present," he said.

Derby’s appointment last year was one of many in terms of new leadership positioned to turnaround the organisation. Transnet also has new executives dealing with procurement and the majority of functions, members of the committee heard. Steps are also being taken to apply consequence management to ensure that wrong doing is not tolerated.

Edited by News24Wire

Comments

Latest News

Magazine round up | 10 May 2024
Magazine round up | 10 May 2024
10th May 2024

Showroom

Avlock International
Avlock International

Avlock International is a leading manufacturer and distributor of Specialized Fastening Systems.

VISIT SHOWROOM 
Booyco Electronics
Booyco Electronics

Booyco Electronics, South African pioneer of Proximity Detection Systems, offers safety solutions for underground and surface mining, quarrying,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 10 May 2024
Magazine round up | 10 May 2024
10th May 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.329 0.385s - 138pq - 2rq
Subscribe Now