Thunderbird mineral sands project, Australia

1st April 2022

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Thunderbird mineral sands project.

Location
Kimberley region, northern Western Australia.

Project Owner/s
Kimberley Mineral Sands (KMS), a 50:50 joint venture between Sheffield Resources and YGH Australia Investment.

Project Description
A bankable feasibility (BFS) has been completed on a simplified process flowsheet for the project, which has resulted in lower capital costs and improved margins for a significant improvement in project economics.

The 2022 BFS has removed the ilmenite processing circuit, which included the low-temperature roaster circuit and ilmenite magnetic separation circuit included in the 2019 bankable feasibility study update.

The BFS flowsheet is expected to produce a nonmagnetic concentrate product containing zircon and rutile, an ilmenite-rich magnetic concentrate and a paramagnetic concentrate.

Thunderbird will be developed in two stages.

Stage 1 and 2 of operations is expected to produce 1.4-million tonnes a year of zircon and ilmenite concentrates over an estimated 36-year life-of-mine (LoM).

The initial Stage 1 mining and processing feed rate is forecast at 1 085 dry tonnes an hour at the wet concentrate plant, with Stage 2 doubling the wet concentrate feed rate to 2 170 t/h during Year 5 of operations.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The BFS delivers a prefinance, after-tax net present value, at an 8% discount rate, of A$1.28-billion and internal rate of return of 27.5% over the LoM.

Capital Expenditure
Stage 1 is estimated at $361-million, including contingency. Total funding requirements for Stage 1 are estimated at A$484-million.

Planned Start/End Date
First production is targeted for the first quarter of 2024.

Latest Developments
Full project financing and a final investment decision on Thunderbird is expected in mid-2022.

Key Contracts, Suppliers and Consultants
GR Engineering Services (engineering, procurement and construction – process facilities).

Contact Details for Project Information
Sheffield Resources, tel +61 8 6555 8777 or email info@sheffieldresources.com.au.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Advanced Fire Suppression Technologies
Advanced Fire Suppression Technologies

Established on 1 March, 2000, by Barries Barnard, Advanced Fire Suppression Technologies (AFST) and the Advanced Group stands as Sub-Saharan...

VISIT SHOWROOM 
Vikela Aluvin (Pty) Ltd
Vikela Aluvin (Pty) Ltd

Complete range of security sealing solutions including security seals bags and labels.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.045 0.996s - 130pq - 2rq
Subscribe Now