https://www.engineeringnews.co.za

Thunderbird mineral sands project, Australia

14th October 2016

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

  

Font size: - +

Name of the Project
Thunderbird mineral sands project.

Location
Australia.

Client
Sheffield Resources.

Project Description
A prefeasibility study (PFS) update on the project has shown significant improvements to the previous PFS study completed in May 2015, which has enhanced Thunderbird’s economics and technical feasibility.

The update is based on a mineral resource of 3.2-billion tonnes, grading 6.9% heavy minerals for 18.5-million tonnes of zircon, 61.8-million tonnes of ilmenite, 6.9-million tonnes of leucoxene and 5.9-million tonnes of HiTi leucoxene.

Sheffield has reported a maiden ore reserve of 683-million, grading 11.3% heavy minerals.

The project’s current mineral resource supports an initial 40-year mine life, with significant scope to increase this in the future. After ramp-up to an 18-million-tonne-a-year throughput, Thunderbird will be one of the world’s largest dry-mining mineral sands operations.

Mining will be conducted using the strip mining and backfill method typically used in dry mining operations in the mineral sands industry. Mining will start with the excavation of an initial pit to expose the ore. As the pit advances, waste overburden and tails will be used to provide a dam wall within the mine void, which will be backfilled with tailings, contoured and rehabilitated.

At the proposed 12-million-tonne-a-year run-of-mine (RoM) feed rate of 1 620t/h, four large dozers will deliver the ore to two 810 t/h skid-mounted dozer trap mining unit plants (MUPs). A third MUP will be on standby to minimise downtime during mine face relocation and maintain consistent throughput. In year eight, throughput will increase to an 18-million-tonne-a-year RoM feed rate of 2 430 t/h by deploying an additional MUP and supporting mobile equipment.

Ore mining will be supported by a fleet of loaders and 100 t trucks. Waste mining, oversize removal, dam wall construction and rehandling will be undertaken using a fleet of loaders, trucks, excavators and scrapers. Low strip ratios in the early years will enable the ore mining fleet to service the waste mining load. The MUPs will screen coarse oversize, with undersize fed to a scrubber trommel. The undersize from the trommel is slurried and pumped to the wet concentrator plant.

The Thunderbird mineralisation will be processed through a conventional heavy mineral sands processing circuit to deliver a suite of zircon, ilmenite, and HiTi88 products. The process includes an ilmenite upgrade using a low-temperature roast (LTR) to upgrade the primary ilmenite by 22% to produce a high-grade (56.1%) sulphate ilmenite.

Overall recovery of ilmenite to product (45% to 47% titanium dioxide) is 74% and overall recovery of LTR ilmenite (56.1% titanium dioxide) is 68%.

Overall zircon recovery, excluding semiprocessed and recirculated streams, has been calculated at 67%. The primary (66.6 zirconium dioxide) zircon is about 80% of the recovered zircon. A secondary (65.1% % zirconium dioxide) and special (62.8% zirconium dioxide) zircon were also produced.

HiTi88 (87.7% titanium dioxide) product recovery, excluding semiprocessed or recirculation streams, is 40%.

Jobs to be Created
Not stated.

Net Present Value/Internal Rate of Return
The project has an estimated payback period of 3.4 years.

Value
The capital cost of the project in the PFS was estimated at $394.1-million; in the update, preproduction capital has been reduced by 26% to A$271-million.

The preproduction capital total includes A$27.7-million for an ilmenite upgrade plant, which will enable Sheffield to produce large quantities of consistently high-quality, high-grade sulphate ilmenite over the 40-year mine life.

Duration
Commissioning of the project is expected in 2018, coinciding with an expected global supply gap.

Latest Developments
Sheffield has started offtake discussions with global ilmenite and zircon customers for its Thunderbird mineral sands project following metallurgical testwork at the project.

The testwork forms part of the project’s bankable feasibility study (BFS), which will be completed in early 2017.

Sheffield MD Bruce McFadzean has described the final results from the metallurgical testwork as "outstanding".

Samples of the product have been dispatched to potential offtake partners for customer testing.

Sheffield is considering a smaller start-up operation in its BFS for the project.

The BFS will be smaller in scope, with throughput planned to start at 7.5-million tonnes a year and ramping up to 15-million tonnes a year from the fourth year of operations.

Sheffield has said that the decreased output will enable the company to capture the benefit of higher head-grade in the project’s early years.

The exact timing of the move to a 15-million-tonne-a-year throughput will be refined in the BFS, in conjunction with marketing initiatives, including discussions with potential offtake partners. The BFS will also consider simplifying the ore processing, which could allow for further capital and operating-cost reductions.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Not stated.

Contact Details for Project Information
Sheffield Resources, tel +61 8 6424 8440, fax +61 8 9321 1710 or email info@sheffieldresources.com.au.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Rio-Carb
Rio-Carb

Rio Carb is an OEM (Original Equipment Manufacturer) of R-C700 Chromium Carbide (CrC) alloy clad wear plates and pipes used for heavy materials...

VISIT SHOWROOM 
Industrial Nozzles & Systems (Pty) Ltd
Industrial Nozzles & Systems (Pty) Ltd

Industrial Nozzles & Systems (Pty) Ltd (Est. 2000) exclusive representative in Southern Africa for LECHLER GmbH (Est. 1879) - Europe's leading...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.049 0.949s - 127pq - 2rq
Subscribe Now