Tall buildings constructed at an increasingly rapid pace

DUBAI'S BURJ KHALIFA 
During the Burj Khalifa building construction period Aurecon identified the need to find quicker ways to construct tall buildings

DUBAI'S BURJ KHALIFA During the Burj Khalifa building construction period Aurecon identified the need to find quicker ways to construct tall buildings

22nd May 2015

  

Font size: - +

Following the construction of the Burj Khalifa 830 m skyscraper in Dubai in 2009, during which the need to find quicker ways to construct tall buildings was identified, global engineering, management and specialist technical services company Aurecon produced a holistic system to enable the construction of a similar building in half the time.

During the Burj Khalifa building construction period, Aurecon identified this need as it noticed that clients and developers did not always have the time to wait for a project to be completed.

“Being able to cut the construction time of a building as tall as the Burj Khalifa in half – or [even] by a third – is a significant achievement,” says Aurecon buildings director for the Middle East and North Africa Dr Andy Davids, who was the chief engineer on the Burj Khalifa project.

“Since then, I have been involved in the design of many megastructures, constructed within mere months,” Davids notes.

Aurecon has found that modular systems – a design approach that subdivides a system into smaller parts called modules that can be independently created and then used in different systems – assist in the construction of taller buildings at a faster pace.

“If you look at existing 400-m- and 500-m-tall buildings, you will see that each one is individually handcrafted and they are each unique and beautiful in their own way. A good observation is that this could be the reason why they take so long to build; however, this is not necessarily true,” says Davids.

He notes that the 30-storey T30 Hotel, in China, was prefabricated and erected in only 15 days.

“This hotel broke national construction management company Broad Group Construction Company’s own past record of building a 15-storey building in just one week.

“This was all possible because modular, prefabricated solutions were used,” Davids says, stating that Aurecon is starting to extrapo- late these principles to expedite the construction of even taller buildings.

“[However,] the goal isn’t to break records, but to deliver a high- performing tall building within a shorter amount of time,” explains Davids.

He notes that the mass production of modules that can be customised according to the needs of each individual client is now a popular means of construction.

Aurecon is able to offer mass customisation to countries, cities and developers who need tall buildings within a shorter timeframe. The company has focused on a modular solution that can be replicated to build additional tall buildings at a quicker speed; however, this does not mean that every building is going to look the same or perform in the same way.

“Design professionals, specifically architects, feel they are less constrained by technology than in the past – and rightfully so. As consulting engineers, it’s our job to use technical skills so that an architect or a client’s vision can be realised,” says Davids.

Edited by Leandi Kolver
Creamer Media Deputy Editor

Comments

Showroom

GreaseMax
GreaseMax

GreaseMax is a chemically operated automatic lubricator.

VISIT SHOWROOM 
Alco-Safe
Alco-Safe

An unmanned breathalyser that is made to be tough and simple to use. Can be used in any environment for operator-free breathalyser testing.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:2.423 2.485s - 152pq - 2rq
Subscribe Now