Spence Growth Option project, Chile – update
Name of the Project
Spence Growth Option (SGO) project.
Location
Spence copper mine, in the Atacama desert, northern Chile.
Project Owner/s
BHP.
Project Description
The SGO project will extend the mine life of the Spence opencut copper mine by more than 50 years. The project will convert 1.3-billion tonnes of measured and indicated mineral resources to hypogene sulphide ore reserves.
The project comprises a conventional large-scale sulphide concentrator for copper and molybdenum, with a nominal ore throughput capacity of 95 000 t/d.
SGO includes a new 1 000 ℓ/sec desalination plant, located at Mejillones Bay, and a 154 km water pipeline from the plant to the Spence mine site. These will be operated by a third party under a build, own, operate and transfer contract.
In the first ten years of operation, incremental production from SGO will be about 185 000 t/y of payable copper in concentrate and 4 000 t/y of payable molybdenum.
Potential Job Creation
About 5 000 jobs were created during the construction phase.
Net Present Value/Internal Rate of Return
The project has an expected internal rate of return of 16% and an expected payback period of 4.5 years from first production.
Capital Expenditure
$2.46-billion.
Planned Start/End Date
The project achieved first production on schedule and on budget in December 2020.
Latest Developments
The project achieved its first copper concentrate production in December 2020, on schedule and on budget, with first copper sales expected in the March quarter of this year.
The ramp-up to full production capacity is expected to take 12 months, at which point Spence will be producing at an average rate of 300 000 t/y over the first four years.
First molybdenum production from Spence is also expected in the middle of this calendar year, following completion of the molybdenum plant.
Key Contracts, Suppliers and Consultants
None stated.
Contact Details for Project Information
BHP investor relations James Wear, tel +1 713 993 3737, email: James.Wear@bhpbilliton.com.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation