Sechaba energy project, Botswana

4th July 2014

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

  

Font size: - +

Name and Location
Sechaba energy project, Botswana.

Client
Shumba Coal.

Project Description
The project involves the development of a 300 MW coal-fired power plant at Shumba Coal’s Sechaba coal project.

Based on the conceptual study on the project, the power plant is envisaged to be configured as a two 150 MW circulating fluidised bed coal-fired power plant. The configuration was chosen, owing to suitability of unit size to the Botswana grid and redundancy offered by the configuration.

Further, the power plant is expected to consist of a subcritical nonreheat steam turbine with dry air-cooled condenser technology. Sulphur oxide (SOx) control will be achieved by in situ SOx capture by limestone dosing in the boiler furnace. Particulate matter control will be achieved with electrostatic precipitators. Nitrogen oxide control is achieved inherently in circulating fluidised bed boilers by virtue of their low operating furnace temperatures.

ValueNot stated.

Duration
Not stated.

Latest Developments
Shumba Coal has concluded design and selection studies, as well as the preliminary financial modelling, for its proposed Sechaba energy project.

Key Contracts and Suppliers
Parsons Brinckerhoff (conceptual studies).

On Budget and on Time?
Not stated.

Contact Details for Project Information
Shumba Coal, tel +267 318 60 72 or email phumaphi@shumbacoal.com.
Parsons Brinckerhoff, tel +1 212 465 5368.

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Sulzer Pumps (SA) (Pty) Ltd
Sulzer Pumps (SA) (Pty) Ltd

Sulzer South Africa, established in 1922, partners with critical industries like power, oil & gas, water, mining, and chemicals to boost...

VISIT SHOWROOM 
WearCheck
WearCheck

Leading condition monitoring specialists, WearCheck, help boost machinery lifespan and reduce catastrophic component failure through the scientific...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.059 1.448s - 145pq - 2rq
Subscribe Now