Sechaba energy project, Botswana
Name and Location
Sechaba energy project, Botswana.
Client
Shumba Coal.
Project Description
The project involves the development of a 300 MW coal-fired power plant at Shumba Coal’s Sechaba coal project.
Based on the conceptual study on the project, the power plant is envisaged to be configured as a two 150 MW circulating fluidised bed coal-fired power plant. The configuration was chosen, owing to suitability of unit size to the Botswana grid and redundancy offered by the configuration.
Further, the power plant is expected to consist of a subcritical nonreheat steam turbine with dry air-cooled condenser technology. Sulphur oxide (SOx) control will be achieved by in situ SOx capture by limestone dosing in the boiler furnace. Particulate matter control will be achieved with electrostatic precipitators. Nitrogen oxide control is achieved inherently in circulating fluidised bed boilers by virtue of their low operating furnace temperatures.
ValueNot stated.
Duration
Not stated.
Latest Developments
Shumba Coal has concluded design and selection studies, as well as the preliminary financial modelling, for its proposed Sechaba energy project.
Key Contracts and Suppliers
Parsons Brinckerhoff (conceptual studies).
On Budget and on Time?
Not stated.
Contact Details for Project Information
Shumba Coal, tel +267 318 60 72 or email phumaphi@shumbacoal.com.
Parsons Brinckerhoff, tel +1 212 465 5368.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation