Scoping study raises Yangibana capital cost estimate

Scoping study raises Yangibana capital cost estimate

Photo by Bloombeg

10th November 2015

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

  

Font size: - +

PERTH (miningweekly.com) – An updated scoping study into the Yangibana rare earths project, in Western Australia, has resulted in a higher capital cost estimate, as well as a shorter mine life.

A 2014 scoping study estimated the project would require a capital investment of A$390-million to deliver around 2 700 t/y of neodymium oxide, 750 t/y of praseodymium, 40 t/y of dysprosium oxide and 70 t/y of europium oxide over a 15-year mine life.

The project was, at that point, estimated to have a net present value (NPV) of between A$900-million and A$1.2-billion.

Hastings Technology Metals on Tuesday said the updated scoping study focused on the production of separated oxides of the rare earths neodymium, praseodymium, dysprosium and europium, with lesser gadolinium and samarium. Additional rare earths could be considered for processing at a later date if suitable market opportunities were identified.

Maintaining the mining rate of one-million tonnes a year, the updated scoping study estimated the project would require a capital investment of A$411-million.

It was estimated that some 45 000 t/y of concentrate would be produced from the Bald Hill South and Fraser’s deposits, while the Yangibana deposit would deliver an additional 70 000 t/y of concentrate, over a seven-year mine life.

Only indicated resources would be mined during the current seven-year mine plan and would deliver a NPV of between A$650-million and A$750-million.

Hastings noted that, based on the mining and processing of some 15-million tonnes of comparable materials, the Yangibana project could return a NPV of between A$900-million and A$1.1-billion. This expanded mining scenario was based on the current inferred resource of 4.2-million tonnes and an exploration target of between four-million and seven-million tonnes.

With the updated scoping study now in place, Hastings was progressing prefeasibility study work on the Yangibana project, with that study due for completion in the first quarter of 2016.

Edited by Chanel de Bruyn
Creamer Media Online Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Latest News

Showroom

Trotech
Trotech

Design, Construction and Maintenance of Site Erected, Welded Bulk Storage Tanks for the Petrochemical, LNG, Ammonia and Sustainable fuel Sectors.

VISIT SHOWROOM 
Condra Cranes
Condra Cranes

ISO-certified Condra manufactures overhead cranes, portal cranes, cantilever cranes and crane components: hoists, drives, end-carriages, brakes and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.05 1.046s - 140pq - 2rq
Subscribe Now