SAPP to prioritise Malawi, Tanzania, Angola for regional grid integration

7th December 2018

By: Marleny Arnoldi

Online News Editor

     

Font size: - +

The Southern African Power Pool (SAPP) will prioritise connecting Malawi, Tanzania and Angola to the regional electricity grid by 2021, with 22 000 MW of electricity generation capacity to be added to the regional grid by 2022.

The SAPP currently serves about 300- million people, with available generation capacity of 59 GW, at a consumption rate of 400 TWh, across 12 member countries, including the Democratic Republic of Congo (DRC), Zambia, Zimbabwe, Mozambique, Botswana, Namibia, eSwatini, South Africa and Lesotho.

SAPP members include national power utilities from every member country, as well as private utilities from some countries.

The generation mix of the SAPP currently comprises 62.05% coal, 2.94% solar photovoltaic, 4.03% wind, 21.02% hydro, 0.97% concentrated solar power, 3.01% nuclear and others.

The

SAPP aims to facilitate the development of a competitive electricity market in the Southern African region.

In the 2017/18 year, trading highlights for the SAPP included a 72% day-ahead market, a 16% intraday market, a 9% forward physical market on a weekly basis, and a 3% forward physical market on a monthly basis.

A total of $106.6-million was exchanged among market players in the reporting year, compared with the $75.8-million exchanged in 2016/17.

During the reporting year, the SAPP traded 76% of its energy bilaterally and 24% through the competitive market. Bilateral trade in the prior year accounted for 88.7% and in the competitive market for 11.3%.

SAPP coordination centre manager Stephen Dihwa said at an SAPP conference, held last week, that the expansion of generation and transmission infrastructure were the biggest challenges facing the SAPP, even though the power pool was the most interconnected of the African power pools.

Economic Consulting Associates partner Peter Robinson expects Southern Africa’s electricity demand to reach 115 GW by 2040, which is an electricity supply rate of 715 TWh.

With this in mind, the SAPP is facilitating the development of a 2 160 MW hydro generation plant in Angola by 2022 and the 2 400 MW Batoka hydro generation plant, in Zambian and Zimbabwe, by 2023, as well as the 1 200 MW Devil’s Gorge hydro generation plant, in Zambia and Zimbabwe, by 2032.

Major Exporter

The DRC is set to become a major exporter of electricity once the Inga 3 and 4 hydro generation plants are developed. There are plans to supply about 4 800 MW by 2030, 9 427 MW by 2033 and 11 600 MW by 2036 from these plants.

Further, Mozambique will commission 1 500 MW by 2028 from Mphanda Nkuwa and Tanzania will commission 1 048 MW by 2036 and 2 036 MW by 2039 from Stiegler’s Gorge.

The

SAPP is continually facilitating major transmission projects from the DRC to Angola, the DRC to Zambia, the DRC to South Africa and Zambia to Tanzania.

Moreover, a panel of speakers at the SAPP conference concurred that political will and harmonising regulation were the biggest challenges to establishing a regionally connected grid.

eSwatini Electrical Company GM Ernest Mkhonta cited the turnover of politicians as a problem across all member countries, which, he said, prohibited the effective and consistent implementation of resource plans.

World Bank Group energy and extractives global practice manager Wendy Hughes echoed that sentiment, adding that harmonising regulation was a necessity, and suggested that a regional regulator be established to ensure coherent implementation of regulations according to the SAPP.

GAIA Infrastructure Capital director Clive Ferreira argued that the SAPP was more of a club than an organisation able to implement plans, and that the SAPP needed greater empowerment before plans could truly add value across countries.

Moreover, ENGIE acquisitions, investments and financial advisory head Desnei Leaf-Camp pointed out that funding was not the issue in Southern Africa, as “the money is there”. “The issue is rather the bankability of the sector, starting from domestic regulation, through to tariff aspects and the consistency of implementation first at national level.”

Edited by Chanel de Bruyn
Creamer Media Online Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

EKATO Africa
EKATO Africa

Established in 1933, EKATO is the world leader in agitation technology, supplying agitators for processes and applications such as chemicals and...

VISIT SHOWROOM 
Flanders Electrical SA
Flanders Electrical SA

FLANDERS Southern Africa provides integrated solutions for mining and industrial operations, covering field services, automation, electrification,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.045 0.757s - 122pq - 2rq
Subscribe Now