Rio Grande liquefied natural gas and Rio Bravo pipeline projects, US

21st June 2019

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Rio Grande liquefied natural gas (LNG) and Rio Bravo pipeline projects.

Location
The facilities will be located in the Jim Wells, Kleberg, Kenedy, Willacy and Cameron counties, Texas, in the US.

Project Owner/s
Rio Grande LNG and Rio Bravo Pipeline Company, wholly owned subsidiaries of NextDecade Corporation.

Project Description
The project involves the construction and operation of:

• six liquefaction trains at the Rio Grande LNG terminal, each with a nominal capacity of 4.5-million tons a year of LNG for export, resulting in the LNG terminal’s nominal capacity of 27-million tons a year;

• four LNG storage tanks, each with a net capacity of 180 000 m3;

• LNG truck loading facilities with four loading bays, each with the capacity to load 12 to 15 trucks a day;

• a refrigerant storage area and truck unloading facilities;

• a condensate storage area and truck loading facilities;

• a new marine slip with two LNG vessel berths to accommodate simultaneous loading of two LNG vessels, an LNG vessel and support vessel manoeuvring area, and an LNG transfer system;

• a materials off-loading facility in the Brownsville ship channel;

• about 4 km of 107-cm-diameter pipeline, including 1.3 km of dual pipeline, to gather gas from existing systems in the Kleberg and Jim Wells counties (referred to as the header system);

• 218 km of parallel 107-cm-diameter pipe-lines originating in Kleberg County and terminating at the Rio Grande LNG terminal in Cameron County (referred to as Pipelines 1 and 2);

• four standalone metering sites along the header system;

• three new compressor stations (one at the LNG terminal site);

• two new interconnect booster compressor stations, each with a metering site; and

• other associated utilities, systems and facilities, such as yards and access roads.

Potential Job Creation
Construction is expected to create between 4 000 and 6 000 jobs.

Capital Expenditure
Not stated.

Planned Start/End Date
NextDecade expects to make a final investment decision on Rio Grande LNG by the end of the third quarter of 2019 and to start commercial operations in 2023.

Latest Developments
The Federal Energy Regulatory Commission issued the final environmental-impact statement for NextDecade’s Rio Grande LNG project.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Too early to state.

Contact Details for Project Information
NextDecade, tel +1713574 1880 or email info@next-decade.com.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

Latest News

Sasol petrol station
Macroeconomic factors dampen Sasol’s year-to-date performance
Updated 1 hour 16 minutes ago By: Marleny Arnoldi

Showroom

Weir Minerals Africa and Middle East
Weir Minerals Africa and Middle East

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 
Aqs image
AQS Liquid Transfer

AxFlow AQS Liquid Transfer (Pty) Ltd is an Importer and Distributor of Pumps in Southern Africa

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 19 April 2024
Magazine round up | 19 April 2024
19th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.131 0.211s - 165pq - 2rq
Subscribe Now