https://www.engineeringnews.co.za

RHA tungsten project, Zimbabwe

30th January 2015

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

  

Font size: - +

Name and Location
RHA tungsten project, Zimbabwe.

Client
Premier African Minerals (49%).

Project Description
The preliminary economic assessment (PEA) on the project was completed in August 2013. The mine plan presented in the PEA consists of an openpit, followed by an underground operation, with a combined life-of-mine of six years at a run-of-mine production rate of 192 000 t/y or 16 000 t/m.

Premier Mining has since commissioned Bara Consulting to update the financial model for the project to demonstrate the effect on the project valuation of the additional work that has been completed since the publication of the PEA. The financial model outlines a low-capital implementation strategy.

Operations will start with an openpit mine, constrained to an 18-month production period, and then progress to underground operations. The project has an updated measured mineral resource of 320 032 t at 6.52 kg/t of tungsten, indicated resources of 1.23-million tonnes at 8.35 kg/t of tungsten, and inferred resources of 1.18-million tonnes at 2.85 kg/t of tungsten.

Net Present Value/Internal Rate of Return
Bara’s financial model reflects a pretax net present value of $15.8-million and an annualised internal rate of return of 286%, calculated on a quarterly basis.

Value
The project has a start-up capital estimate of $4.15-million from $4.77-million.

Duration
Production is assumed to start in April, with pit preparation starting in March.

Latest Developments
An implementation study report on the low-capital openpit start-up strategy for Premier African Minerals’ RHA Tungsten project has determined a lower estimated preproduction capital cost of $4.15-million.

In October last year, the Aim-listed company provided details of the start-up strategy, which had set out an initial estimated preproduction capital requirement of $4.77-million.

Premier has highlighted that the implementation study report has maintained the June 2015 targeted date for first production, while operating costs have been reduced to $89.1 a metric tonne unit (mtu) of tungsten trioxide (WO3).

“The report confirms our strategy for RHA and supports our conclusions that the openpit is projected to generate sufficient surplus cash to allow for the start of repayment of loans to be made to RHA by Premier, and to finance the build of the underground operations,” says Premier CEO George Roach.

He further notes that Premier is still in negotiating potential additional funding for the project.

Further, while the company has been offered offtake agreements for WO3 over the life of the mine, it will investigate other alternatives given the fact the mine has the potential to be “a significant, stable and long-term producer”.

The RHA project is expected to process 8 000 t/m of run-of-mine ore and produce, on average, 92 t/m of concentrate at 63% WO3 over a 22-month period.

Meanwhile, Premier has placed an order for a $2.2-million processing plant for the RHA tungsten project, advancing the miner’s goal of reopening the mine.

The process plant is designed to meet a throughput of 16 t/h, or 8 000 t/m, and is expected to support wolframite recovery of 82.8%.

This production rate excludes any consideration of a preconcentration circuit which, if implementead in future, could increase the plant throughput fivefold at a 20% recovery loss.

The modular plant will be built in Johannesburg by Appropriate Process Technologies, after which the modules will be containerised and trucked to site, where the process plant is expected to be fully commissioned by mid-2015.

Key Contracts and Suppliers
Bara Consulting (updated financial model).

On Budget and on Time?
Not stated.

Contact Details for Project Information
Premier African Minerals, tel +27 100 201 281 or email info@premierafricanminerals.com.

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Airshrink - CiP
Airshrink - CiP

At Airshrink - CiP, we surpass customer expectations with innovative MV and LV cable accessories, including heat shrink joints, terminations,...

VISIT SHOWROOM 
AirNox Pty Ltd
AirNox Pty Ltd

AirNox (Pty) Ltd is a level 1 BBBEE manufacturer of complete AdBlue® solutions for operators of SCR diesel engines and AUS40 across South Africa...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.073 0.393s - 147pq - 2rq
Subscribe Now