Ramelius develops plan to deal with pit wall failure
PERTH (miningweekly.com) – Gold miner Ramelius Resources on Monday told shareholders that it had devised a plan to resolve a wall slip at its Western South Queen openpit mine, in Western Australia, which resulted in the miner suspending operations last week.
The slip occurred beneath the ramp on the western side of the pit.
Ramelius said that while part of the pit ramp was affected by the slip, access to the bottom of the pit was still possible.
The miner had now developed a plan to rectify the slip area, but warned shareholders that the work would not start until safe working conditions existed. The work would also take about 14 days to complete.
Despite the pit wall failure, production at the Western Queen would not be impacted in the short term, as the operation already had a four-month supply of stockpiled ore which would be delivered to the Mount Magnet mill.
Last month, Ramelius was forced to stop production at its Mount Magnet project, after electrical projects were reported at its processing plant. A temporary replacement motor was installed; however, the motor was running below the previous capacity, meaning that the processing plant was operating at only 85% capacity.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation