Power plant decommissioning not due to IPPs, Radebe asserts
State-owned power utility Eskom will not be closing its own coal plants to accommodate the offtake requirements of the coal independent power producers (IPPs), Energy Minister Jeff Radebe has said.
“Eskom’s policy on the decommissioning of its fleet is informed by an optimal balance of cost efficiencies, reduced capacity and carbon emission considerations,” he said in a Parliamentary response this month.
He added that Eskom’s planned decommissioning of the Arnot, Camden, Grootvlei, Hendrina and Komati coal-fired power stations had already been projected in the Integrated Resource Plan 2010, which indicated that the decommissioned capacity would be replaced by about 8 800 MW of new coal-fired power generation capacity through Kusile and Medupi.
Rapid Deterioration Moreover, he pointed out that the efficiency of Eskom’s older coal-fired power plants had deteriorated rapidly and that these plants cost substantially more to operate, resulting in a spillover into tariff increases.
Radebe said government’s energy policy was premised on a balanced energy mix that recognised the country’s natural endowment of energy carriers, including coal.
Moreover, the Minister, in reply to a question raised around Eskom’s electricity production, remarked that Eskom was not required to produce less electricity as a consequence of IPPs.
“The wind and solar photovoltaic technologies introduced through the renewable-energy programme do not displace coal-fired power stations, as these technologies do not provide baseload capacity,” he said.
Radebe was, meanwhile, also asked whether two coal IPPs would give rise to at least 5 000 jobs during construction.
He replied that, in terms of the bids received in response to the request for proposals (RfP) for coal IPPs, the preferred bidders had set out 7 943 jobs for Project 1 and 2 377 jobs for Project 2, both during the construction phase.
Jobs during operations, as set out in the bids, included 10 678 for Project 1 and 4 626 for Project 2. These figures were calculated on the basis that one job equated to 12 person months and one person month to 160 working hours.
“If one were to assume the construction period to be four years, with the operations period being 30 years, the total direct jobs during construction would be equivalent to having about 2 580 people working for four years during construction and about 510 people working for 30 years during operations,” he explained.
However, since jobs were provided in job years in accordance with the RfP, the figures were likely to be understated.
Further, Radebe noted the job numbers directly associated with the coal IPP plants did not include the indirect jobs created as a result of the new mine, which one of the projects would be dependent on, as well as the jobs created in relation to the discard coal supply, which the other project would be using.
The job numbers also excluded indirect job creation in respect of manufacturing and limestone supply.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation