https://www.engineeringnews.co.za

Qala Shallows Phase 1 project, South Africa

28th October 2022

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Qala Shallows Phase 1 project.

Location
At the northern edge of the Witwatersrand basin, in the Central Rand Goldfield, immediately south-west of the City of Johannesburg, in Gauteng, South Africa.

Project Owner/s
West Wits Mining.

Project Description
The Qala Shallows Phase 1 project forms part of West Wits’ Witwatersrand Basin project.

A revised definitive feasibility study (DFS) completed in August 2022 has confirmed earlier increased production build-up and improved financial results.

The revised DFS envisages a 7.6-million-tonne run-of-mine operation with a maximum production rate of 699 000 t/y.

The project will have a life-of-mine (LoM) of 15.7 years from construction to relinquishment, with peak steady-state production estimated at 55 000 oz/y over a ten-year period. The mine will average 43 000 oz/y of gold over the LoM.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project’s pretax net present value has increased from $151-million, at a 7.5% discount rate in the 2021 DFS, to $180-million, at a 7.5% discount rate, in the revised 2022 DFS.

The internal rate of return has increased from 35% in the 2021 DFS to 38% in the revised 2022 DFS.

Payback has decreased from 5.5 years to 5 years.

Capital Expenditure
Peak funding has increased from $48-million in the 2021 DFS to $63-million in the revised 2022 DFS.

The increase in peak funding is mainly owing to the accelerated production build-up, which requires additional mining equipment and underground development at an earlier stage of the project.

Planned Start/End Date
A rapid production ramp-up is planned for the fourth quarter of 2022 as part of a formal mine plan under the revised DFS.

Latest Developments
West Wits is working on the execution of a long-term toll treatment agreement.

Key Contracts and Suppliers
Modi Mining (mining contract); and Bara Consulting (LoM production profile).

Contact Details for Project Information
West Wits Mining, tel +61 3 8692 9049 or email info@westwitsmining.com.

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Sika South Africa
Sika South Africa

Sika South Africa is a trusted partner for the nation’s infrastructure, commercial, residential, and industrial sectors.

VISIT SHOWROOM 
Werner South Africa Pumps & Equipment (PTY) LTD
Werner South Africa Pumps & Equipment (PTY) LTD

For over 30 years, Werner South Africa Pumps & Equipment (PTY) LTD has been designing, manufacturing, supplying and maintaining specialist...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.053 1.275s - 147pq - 2rq
Subscribe Now