Polymetal produces first gold at Kutyn mine

Refractory ore will be processed at the Albazino concentrator, starting in 2025.
Gold and silver miner Polymetal has produced its first gold at the Kutyn mine, in Far East Russia – six months ahead of the schedule, but 38% above the original capital expenditure (capex) budget.
“Remote location, severe climate, and unprecedented supply chain disruptions presented major challenges at Kutyn,” CEO Vitaly Nesis said on Tuesday.
Following successful completion of construction and commissioning activities, Kutyn heap leach facility produced first 6 000 oz of gold. In 2022, production is expected to amount to 40 000 oz of gold.
Full heap leach processing capacity of 1.3-million tonnes a year of ore will be reached in 2023.
Processing of the refractory ore at Albazino concentrator will start in 2025. Average output from 2023 to 2030 will be about 100 000 oz/y of gold with average all-in sustaining cost of $950/oz.
The project’s capex came in 38% above the original estimate at $110-million, with the overrun mostly owing to expanded, higher fuel prices and Covid-19 impact on logistics and labour costs.
Jorc-compliant ore reserves at Kutyn are estimated at 12-million tonnes of openpit oxide and refractory ore containing 1.1-million ounces of gold-equivalent (GE) at a grade of 2.9 g/t. Additional resources amount to 2.5-million tonnes of ore containing 414 000 oz of GE at 5.1 g/t.
Kutyn deposit is located 114 km northwest of the Albazino mine.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation