Orbite shares slip on plant budget blowout, construction delays

7th June 2013

By: Henry Lazenby

Creamer Media Deputy Editor: North America

  

Font size: - +

TORONTO (miningweekly.com) – Canadian alumina producer Orbite Aluminae’s TSX-listed stock on Friday slipped 18.18% to $0.72 apiece, after the company on Thursday said it would cost $20.9-million more to complete the 3 t/d second phase of its high-purity alumina (HPA) plant, in Cap-Chat, Quebec.

In its management discussion and analysis of December 2012, Orbite said the plant was expected to cost $85-million, and as at March 31, the company had already spent $74.9-million. Orbite obtained independent cost estimates to complete the project, which put the cost at $105.9-million, including $6.7-million for contingency and for critical spare parts.

The updated capital cost estimate represented the investment required to achieve the Phase 2 production capacity of 3 t/d. Orbite said a large portion of the HPA plant had been designed at a 5 t/d capacity and, as such, the requisite engineering analysis to increase the total plant throughput to 5 t/d, as well as to add a scandium and gallium separation facility, was expected to be completed during the second half of the year and the incremental capital cost estimate was expected to be reported during the first quarter of 2014.

Orbite extended the expected project timeline by six months to the end of the second quarter of 2014.

The company had also appointed Denis Arguin as VP for operations.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Astore Keymak
Astore Keymak

Astore Keymak is one of South Africa’s leading suppliers of high-quality Thermoplastic Pipeline Systems, with branches in the major provinces.

VISIT SHOWROOM 
M and J Mining
M and J Mining

M and J Mining are leading suppliers of physical support systems as used by the underground mining industry. Our selection of products are not...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.057 0.973s - 140pq - 2rq
Subscribe Now