https://www.engineeringnews.co.za

New Acland Stage 3 coal mine expansion project, Australia – update

7th January 2022

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
New Acland Stage 3 coal mine expansion project.

Location
Queensland, Australia.

Project Owner/s
New Acland Coal (NAC), a subsidiary of the New Hope Group.

Project Description
NAC operates the existing New Acland coal mine as a 4.8-million-tonne-a-year opencut coal mine on mining lease (ML) 50170 and ML 50216. The mine has reserves that will allow for current operations to continue until about 2017.

The project will expand the mine’s yearly output from 4.8-million tonnes to 7.5-million tonnes and will extend the operation’s life beyond the current end-date of 2017/18.

The revised coal project proposes to develop Stage 3 of the New Acland mine, which involves the extension of the mine’s operating life to about 2029, including the progressive development of two new resource areas within the area covered by Mining Development Licence 244, also covered by ML application 50232.

The two resource areas will be developed sequentially and, combined with the current operations, will supply up to 7.5-million tonnes a year of saleable product coal for the export and domestic markets until about 2029.

Key features of the project include:

  • developing parts of the Manning Vale and Willeroo resource areas;
  • upgrading the existing coal handling and preparation plant and supporting infrastructure;
  • constructing a new coal load-out facility on the mining lease and an estimated 8 km rail spur, as a result of the relocation of the existing Jondaryan coal load-out facility;
  • roadworks and constructing water management structures; and
  • relocating and potentially upgrading the power supply to the revised project.

The Acland town area, including Tom Dohertypark, the War Memorial and the Acland No 2 colliery and utility services, will be maintained over the life of the revised project.

The closest point of potential mining operations will be at least 10 km away from Oakey, compared with the 7 km previously proposed.

The land disturbed for mining activities will be reduced by more than half, compared with the original Stage 3 proposal.

Veneering to coat all transported coal leaving the mine by train as a measure to reduce the potential for coal dust coming from trains will continue.

Lagoon Creek will not be diverted as previously proposed. Operations will continue to be self-sufficient for water, with water continuing to be bought from Toowoomba’s Wetalla wastewater reclamation facility. Only about 20% of the Wetalla water is bought by NAC.

Production levels from the New Acland mine will be reduced by at least 25% to 7.5-million tonnes a year from the originally proposed ten-million tonnes a year.

Potential Job Creation
Once approved, the New Acland Stage 3 project will create 187 new jobs within the first six months and 487 jobs within 18 months.

Net Present Value/Internal Rate of Return
Not stated.

Capital Expenditure
A$900-million.

Planned Start/End Date
About 2.5 years will be required to complete the design and build the mine, as well as other activities to facilitate the revised project.

Latest Developments
The Queensland Land Court recommended in December 2021 that the New Acland Mine Stage 3 mining leases and the environmental authority amendment application be granted, subject to conditions, with the Queensland Resources Council (QRC) now calling for the project approvals to be granted.

New Hope Corporation has said that it will continue to work with the relevant Queensland government departments to progress the Stage 3 approvals applications and seek to secure their grant as soon as possible.

The QRC has welcomed the decision by the Land Court, with CEO Ian Macfarlane saying it has taken 14 years for the project to finally reach this stage, with the initial development application lodged by New Hope Group in 2007.

Key Contracts, Suppliers and Consultants
Not stated.

Contact Details for Project Information
New Acland Coal, tel +61 7 3418 0500, fax +61 7 3418 0355 or email aclandinfo@newhopegroup.com.au.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

ABB Electrification
ABB Electrification

Electrifying the world in a safe, smart, and sustainable way, ABB Electrification is a global technology leader in electrical distribution and...

VISIT SHOWROOM 
EKATO Africa
EKATO Africa

Established in 1933, EKATO is the world leader in agitation technology, supplying agitators for processes and applications such as chemicals and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.053 1.207s - 127pq - 2rq
Subscribe Now