New 122 MW gas-fired Moz power plant to start production in Q2

14th March 2013

By: Creamer Media Reporter

  

Font size: - +

Temporary power and temperature control solutions provider Aggreko is expanding the power generation capacity at Gigawatt Park, in Ressano Garcia, Mozambique, to 232 MW at a cost of more than $200-million, including fuel costs.

Aggreko built the facility at Ressano Garcia with an initial capacity of 110 MW, in 2012, as part of an ambitious project in which it became the first cross-border, interim independent power provider to the Southern African Power Pool (SAPP).

The first phase of the project, undertaken in collaboration with joint venture partner Shanduka, ensured the supply of power to Electricidade de Moçambique (EDM) for national energy requirements in Mozambique, as well as to South African power utility Eskom.

The success of this initial phase has enabled Aggreko to offer additional power to other members of the SAPP.

The new 122 MW gas-fired plant at the Ressano Garcia facility would start production in the second quarter of this year and would supply power for at least two years.

The Matola Gas Company would supply natural gas to the plant, enabling Aggreko to generate power using a subconcession agreement with Gigawatt Mozambique.

Aggreko on Thursday announced that it had signed a tri-party power purchase agreement with power utilities EDM and NamPower, which would use up to 32 MW and up to 90 MW of the additional power capacity respectively.

The agreement followed the authorisation by EDM for the direct supply of power by Aggreko to NamPower.

Both EDM and Eskom would play a key role in delivering the power to Namibia.

EDM would transmit the power over its network to the South African border where NamPower would take delivery. Eskom, on behalf of NamPower, would handle the wheeling of the power across the South African grid to Namibia.

“This new project will make Ressano Garcia the world’s largest cross-border interim power plant, with over 232 MW of gas-fuelled power generation. It underlines the immense potential of the SAPP to be a real conduit of cooperation and development among the countries of Southern Africa.

“The fact that three national utilities are collaborating to support each other’s energy requirements is testament to the benefit of working together for the common good,” commented Aggreko CEO Rupert Soames.

Edited by Chanel de Bruyn
Creamer Media Online Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Astore Keymak
Astore Keymak

Astore Keymak is one of South Africa’s leading suppliers of high-quality Thermoplastic Pipeline Systems, with branches in the major provinces.

VISIT SHOWROOM 
Monitor Distributors
Monitor Distributors

We at Hawk High Pressure Pumps specialise in industrial pumps and pumping systems. Our high pressure washing equipment is locally manufactured and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.051 1.46s - 159pq - 2rq
Subscribe Now