https://www.engineeringnews.co.za

Ncondezi coal-to-power project, Mozambique

15th June 2018

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Ncondezi coal-to-power project.

Location
The 38 700 ha Ncondezi licence area is located in Mozambique's coal-bearing Tete province, one of the largest undeveloped coal mining regions in the world.

Client
Ncondezi Power Company (NPC).

Project Description
Ncondezi's Joint Ore Reserves Committee-compliant coal resource amounts to 4.7-billion tons, permitting a large and long operation. The Phase 1 power plant will use Mozambique’s present transmission network, reinforced, to carry its output to consumers. Only about 20% of the country is currently electrified and the acceleration and expansion of electrification have become government policy.

The Ncondezi mine forms part of the integrated thermal coal mine and power plant project. The power station is expected to initially produce 300 MW, of which 60 MW will be used to operate the power plant, and 240 MW will be supplied to the northern electricity grid for use by consumers across Tete.

Being built in phases, the power plant project has been designed to be scalable up to a planned maximum capacity of 1 800 MW.

The Ncondezi mine will be the base for the project, and the power plant will be located on the mining concession. The mine will be able to supply 1.1-million tons of coal a year, with an energy-producing capacity of 18.66 MJ/kg for 25 years.

The openpit mine will be 2 km away from the power plant and will have a lifetime capacity of 4.8-billion tons of coal. The coal from the mine – still at a lower quality than export-grade thermal coal – will have to be processed to achieve the desired grade of 18.66 MJ/kg before it can be used by the Ncondezi power plant.

Ncondezi Energy will consider exporting coal when the price of seabourne coal and access to rail and port infrastructure improve in the future.

Further, some of the other lower-quality coal from the surrounding mines in Tete might also be used to bolster the power station’s coal supply.

Potential Job Creation
During the construction of the Ncondezi power plant and mine, an estimated 2 000 jobs will be created. Once construction of the mine is completed, it will provide 50 permanent jobs, while the power plant will provide more than 200 permanent positions.

Net Present Value/Internal Rate of Return
Not stated.

Value
The estimated cost of the power plant is $1-billion and that of the mine between $60-million and $80-million.

Duration
Construction of the mine and power plant will start simultaneously, with the power plant estimated to take three years to complete and the coal mine two years. Once the mine starts operations, it will accumulate a stockpile of coal for the power station to use once it has been completed.

Latest Developments
The joint development agreement (JDA) for Ncondezi Energy’s integrated 300 MW power and coal mine project is nearing completion.

The company’s integrated financial model has been accepted by potential partners and company stakeholders for submission to Mozambique energy company Electricidade de Moçambique and Mozambique’s Mineral Resources and Energy Ministry.

This submission is targeted for this month to seek in-principle support for a new power tariff envelope thereafter.

The financial model represents a key milestone in confirming the project economics, restarting tariff negotiations and completing the JDA process, Ncondezi has said.

“Positive results from the financial model indicate that project economics can be maintained with a more than 10% reduction in the previously agreed tariff envelope.

“A reversed tariff proposal strengthens the commercial negotiating position of the project,” the company has stated.

According to the financial model, the project could have financial benefits of between $1.1-billion and $1.4-billion in tax receipts and royalties over the life of the project.

The coal-fired project is expected to start delivering power into the grid in 2022.

Key Contracts and Suppliers
KPMG (mine feasibility study), Impacto and Environmental Resources Management Southern Africa (environmental- and social-impact assessment) and the Mineral Corporation (geological consultant).

On Budget and on Time?
Too early to state.

Contact Details for Project Information
NPC corporate development manager Hanno Pengilly, tel +44 20 7183 5402 or email info@ncondezicoal.com.
 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Vikela Aluvin (Pty) Ltd
Vikela Aluvin (Pty) Ltd

Complete range of security sealing solutions including security seals bags and labels.

VISIT SHOWROOM 
Sulzer Pumps (SA) (Pty) Ltd
Sulzer Pumps (SA) (Pty) Ltd

Sulzer South Africa, established in 1922, partners with critical industries like power, oil & gas, water, mining, and chemicals to boost...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.051 0.989s - 147pq - 2rq
Subscribe Now