https://www.engineeringnews.co.za
Africa|Aveng|Building|Cable|Concrete|Construction|Consulting|Consulting Engineers|Cutting|Design|Environment|Installation|PROJECT|Projects|Road|Roads|Safety|SECURITY|SMEC|Environmental|Cables
Africa|Aveng|Building|Cable|Concrete|Construction|Consulting|Consulting Engineers|Cutting|Design|Environment|Installation|PROJECT|Projects|Road|Roads|Safety|SECURITY|SMEC|Environmental|Cables
africa|aveng|building|cable|concrete|construction|consulting-company|consulting-engineers|cutting|design|environment|installation|project|projects|road|roads|safety|security|smec|environmental|cables

N2 Wild Coast Toll Road megabridge projects, South Africa – update

Artist rendering of the Mtentu Bridge

11th August 2023

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
N2 Wild Coast Toll Road (N2WCTR) megabridge projects. 

Location
The bridges will be built over the Msikaba and Mtentu river gorges, both near Lusikisiki, in South Africa’s Eastern Cape province.

The Msikaba bridge is located on the N2, which connects the Western Cape, Eastern Cape, KwaZulu-Natal and Mpumalanga provinces, and traverses the cities and major towns of Cape Town, George, Gqeberha (formerly Port Elizabeth), East London, Mthatha, Durban and Ermelo. This includes a new greenfield section of 112 km between Port St Johns and Port Edward, including the two megabridges and several additional major river interchange bridges.

Only the new greenfield section of the project will be tolled. None of the sections between East London and Mthatha or between Mthatha and Ndwalane, near Port St Johns, will be tolled. The public participation process for the tolling of the greenfield section of the road is yet to start.

Project Owner/s
South African National Roads Agency Limited (Sanral).

Project Description
The Msikaba and Mtentu bridges form part of the N2WCTR project.

The 580-m-long Msikaba bridge will be the longest main span bridge in Africa – constructed using the cable-stayed method – and the second-longest main bridge span in Africa after the Maputo-Catembe suspension bridge, in Mozambique. With a deck height of 194 m above the river valley, Msikaba will become the third-highest bridge in Africa and the 133rd-highest in the world. The Msikaba bridge cable-stay design will ensure that the construction of the bridge will have no direct impact on the pristine gorge environment almost 200 m below, which is one of the environmental requirements for building the bridge.

The bridge is being built from the north and south banks of the gorge and comprises two identical halves, each spanning 290 m, which will meet midpoint over the gorge. 

Each half is supported by 17 pairs of cables attached to the inverted Y-shaped pylons, one on each side of the gorge. 

The pylons are back-stayed into the anchor blocks, two on either side of the gorge, by 34 pairs of cables – 17 for each half – positioned 130 m behind each pylon. 

Each anchor block is 49 m long, 10 m wide at the base (narrowing to 4 m on the spine of the structure), 17.2 m deep, and a mass of 21 500 t. 

The 1.13-km-long Mtentu bridge, which includes a 260-m-long main span, will be one of the longest main-span-balanced cantilever bridges in the world. Only ten prestressed concrete girder bridges worldwide have a main span of 260 m or longer. Reaching heights of more than 220 m above the river valley, it will displace the Bloukrans bridge, in the Western Cape, as the highest bridge in Africa and the southern hemisphere. The 141-m-tall Pier No 9 (equivalent to a 40-storey building in height) will also be the tallest bridge pier in Africa and the southern hemisphere.

Being one of the longest main-span-balanced cantilever bridges and one of the highest bridges in the world makes the construction of the Mtentu bridge a technically highly challenging project. The remote location and local social dynamics add to this complexity.

Potential Job Creation
So far, the Msikaba project has created work for 137 unskilled local labourers and 372 jobs for skilled persons, of whom 190 are locals.

The Mtentu Bridge contract has a local labour contract participation goal of 4%. This should result in a minimum of R141-million (excluding VAT) being paid to local labour in wages and salaries, creating a minimum of 1 080 full-time employment jobs for local skilled and unskilled persons during the contract period.

Capital Expenditure
The Msikaba bridge project will cost an estimated R1.65-billion and the Mtentu bridge project R4.5-billion.

Planned Start/End Date
The N2WCTR project started construction in 2011. However, the major greenfield portion of the route between Port St Johns and Port Edward started construction only in 2016.

Construction of the Msikaba bridge is expected to be completed at the end of 2024.

Provided that there are no significant delays on the Mtentu bridge project, construction of the bridge is expected to take 50 months, with the project expected to be completed at the end of 2027.

Latest Developments
The South African National Roads Agency Limited (Sanral) has announced the restart of construction work on the Mtentu bridge contract.

The Aveng Strabag joint venture (JV), responsible for building the then R1.6-billion structure, walked out on the project in early 2019, following months of violent community protests.

The scope of the new Mtentu tender has been expanded from the original terminated contract to include the upgrading of 18 km of provincial road, linking the future Mkhambati interchange to the Flagstaff–Holy Cross road, while also providing for a direct link from the future N2 to the town of Flagstaff, as well as the construction of three nearby community access roads.

The new Mtentu contract was awarded to the China Communications Construction Company and MECSA Construction joint venture on November 1, 2022.

The restart follows a four-month mobilisation period, which started on April 5 and ended on August 4.

Fifteen general workers will start with construction of the site offices, while 30 general labourers will undergo medical and safety induction. They will then also start site clearance and grass cutting. 

Construction of boreholes on the north and south banks will begin on August 15, while construction of toilets, installation of security measures and the relocation of affected households will start on September 1.

Key Contracts, Suppliers and Consultants
Concor Mota-Engil, a JV between Concor Construction and MECSA Construction (Msikaba bridge contract); HVA JV (Msikaba and Mtentu bridge consultants comprising CH2M and SMEC); V3 Consulting Engineers (lead consultant – Ndwalane to Ntafufu and Kulumbe to Mtamvuna river); ERO Engineers (lead consultant – Ntafufu to Bambisana turn-off); Naidu Consulting (lead consultant – Bambisana turn-off to Lingeni); Aurecon Rohm consortium (lead consultants – Lingeni to Msikaba); Knight Pieésold (lead consultant – Msikaba to Mtentu); and KBK Engineers (lead consultant – Mtentu to Kulumbe).

Contact Details for Project Information
Sanral project manager Craig McLachlan, tel +27 41398 3200 or email MclachlanC@nra.co.za.

Edited by Creamer Media Reporter

Comments

Showroom

GreaseMax
GreaseMax

GreaseMax is a chemically operated automatic lubricator.

VISIT SHOWROOM 
Booyco Electronics
Booyco Electronics

Booyco Electronics, South African pioneer of Proximity Detection Systems, offers safety solutions for underground and surface mining, quarrying,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (26/04/2024)
26th April 2024 By: Martin Creamer
Magazine cover image
Magazine round up | 26 April 2024
26th April 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.11 0.186s - 165pq - 2rq
Subscribe Now