Project Description
An updated scoping study on the Mt Carrington project has delivered a significant uplift in project economics.
The preferred processing flowsheet for the project will consist of:
• a central run-of-mine (RoM) pad, with an RoM bin and primary crusher fed by a front-end loader;
• a coarse ore stockpile, with a reclaim conveyor;
• a lime addition silo on the conveyor feeding the grinding circuit;
• a grinding circuit, requiring about 1800 kW of grinding power, possibly comprising a semiautogenous mill and ball mill, and a regrind ball mill of 200 kW to 250 kW;
• a flotation circuit to concentrate the gold and silver sulphides;
• a cyanide leach and carbon adsorption circuit;
• a standard elution and electrowinning circuit; and
• a gold room, a reagents area, a small lab and workshop.
In Year 3, the silver-dominant pits will be brought into the mine plan. Incremental capital will be spent on the flotation circuit to include a cleaner step, dewatering and concentrate production facility.
Net Present Value/Internal Rate of Return
The project has a net present value, at a 10% discounted rate, of A$60.6-million and a internal rate of return of 103% with a payback of ten months.
Value
The capital cost of the project is estimated at A$24.2-million.
Duration
The scoping study evisages an estimated 12-month design, build and commissioning period.
Latest Developments
White Rock estimates that the feasibility study will take 12 months.
This work will include process design testwork and flowsheet optimisation, mine plan (pit) optimisation and further engineering design and costings.
In parallel, the environmental-impact statement will be completed, allowing for permitting from the regulatory authorities to be acquired within 18 to 24 months.
Key Contracts and Suppliers
None stated.
On Budget and on Time?
Not stated.
Contact Details for Project Information
White Rock Minerals, email info@whiterockminerals.com.au.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation