Molo graphite project, Madagascar
Name of the Project
Molo graphite project.
Location
The project is located in southern Madagascar.
Project Owner/s
NextSource Materials.
Project Description
The project has proven and probable reserves of 22.44-million tonnes grading 7% carbon. Total measured and indicated minerals resources are estimated at 100.37-million tonnes grading 7.7% carbon.
An updated feasibility study has outlined a phased development approach for the project.
The first phase of production will comprise a fully operational and sustainable graphite mine, with a permanent processing plant capable of processing 240 000 t/y of ore and producing about 17 000 t/y of high-quality SuperFlake graphite concentrate.
After the first two years of operation, Phase 2 incorporates the ramping up to 720 000 t/y of processed ore in the third year to accommodate additional sales, resulting in 45 000 t/y of SuperFlake concentrate being produced for a mine life of 30 years.
Potential Job Creation
An estimated 180 jobs are expected to be created.
Net Present Value/Internal Rate of Return
The project has a pretax net present value, at an 8% discount rate, of $237.1-million and an internal rate of return of 43.1%, with a payback of 3.4 years.
Capital Expenditure
Capital expenditure (capex) for Phase 1 will be $21-million, with Phase 2 capital expenditure being an additional $39.1-million, for a total project cost of $60.1-million.
Planned Start/End Date
Once capital expenditure is secured, construction will take only nine months.
Latest Developments
The recently updated feasibility study positions Molo as a very high-quality and economic project with one of the lowest capex costs in the industry.
One-hundred per cent of Phase 1 production has been secured through a ten-year binding offtake agreement with the primary graphite supplier to a major Japanese electric anode producer.
Key Contracts and Suppliers
None stated.
On Budget and on Time?
Too early to state.
Contact Details for Project Information
NextSource Materials, tel +1 416364 4911 or email info@nextsourcematerials.com.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation