Name of the Project
Matilda/Wiluna gold operation expansion project.

Location
The Matilda/Wiluna gold operation is located in Australia’s largest gold belt, which stretches from Norseman to Wiluna and passes through Kalgoorlie and Leinster.

Client
Blackham Resources.

Project Description
The operation has Joint Ore Reserves Committee-compliant resources of 61-million tonnes grading 3.1g/t for 6.1-million ounces of gold within a 20 km radius of the Wiluna gold plant.

An expansion prefeasibility study (PFS) on the operation has shown robust economics and improved economies of scale supporting the operation’s expansion.

The expansion PFS has focused on the Wiluna openpits and underground operations, as well as on incorporating the existing Matilda, Quartz Reef and Lake Way reserves and mining inventory. It is presupposed that the expanded operation will be developed through:
• the construction of a new crushing and grinding circuit to increase throughput by 1.5-million tonnes a year;
• the construction of a new flotation circuit;
• the refurbishment of the existing sulphide treatment plant, which has operated for 20 years; and
• the construction of a new carbon-in-leach circuit.

The expansion PFS envisions an economic plan to process oxide ore (1.8-million tonnes a year) and sulphide ores (1.5-million tonnes a year) for a combined processing capacity of between 2.3-million tonnes a year and 3.3-million tonnes a year.

An initial 1.47-million ounces will be mined over nine years, averaging 207 000 oz/y of gold.

Jobs to Be Created
Not stated.

Net Present Value/Internal Rate of Return
The project has a net present value, at an 8% discount rate, of $360-million and an internal rate of return of 123%.

Value
The PFS estimates that the expansion will cost A$113.9-million.

Duration
The expansion is expected to take about 15 months from the start of construction and is expected to be completed in June 2019.

Latest Developments
An expansion definitive feasibility study (DFS) is under way, with key work well advanced. The DFS is targeted for completion in the first quarter of 2018.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Not stated.

Contact Details for Project Information
Blackham Resources, tel +61 8 9322 6418, fax +61 8 9322 6398 or emailinfo@blackhamresources.com.au.

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Sika South Africa
Sika South Africa

Sika South Africa is a trusted partner for the nation’s infrastructure, commercial, residential, and industrial sectors.

VISIT SHOWROOM 
Werner South Africa Pumps & Equipment (PTY) LTD
Werner South Africa Pumps & Equipment (PTY) LTD

For over 30 years, Werner South Africa Pumps & Equipment (PTY) LTD has been designing, manufacturing, supplying and maintaining specialist...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.059 0.968s - 147pq - 2rq
Subscribe Now