Madaouela uranium project, Niger

Location map of the Madaouela uranium project

Photo by GoviEx

9th December 2022

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

This article has been supplied.

Name of the Project
Madaouela uranium project.

Location
Agadez region, northern Niger.

Project Owner/s
GoviEx.

Project Description
The project hosts one of the biggest uranium resources in the world, with 100-million pounds of uranium in measured and indicated mineral resources, and inferred resources of 20-million pounds of uranium.

The mineral resources comprise the Miriam, M&M, MSNE, MYVE, MSEE and MSCE sandstone-hosted uranium deposits

The project is based on a self-sustaining operation, including process plant and renewable power supply, without any reliance on third-party facilities.

Mining operations for the project are planned to be based on standard truck-and-shovel openpit mining for the Miriam deposit at one-million tonnes a year of ore feed to the process plant.

The M&M and MSNE-Maryvonne deposits are planned to be mined as two separate underground room-and-pillar operations. M&M is to be mined first after the completion of the Miriam openpit operation, with MSNE-Maryvonne mined after M&M.

At both underground operations the mine development and ore production operations are planned to be mined using conventional drill-and-blast methods. The process plant is designed around two-stage acid leaching to maximise uranium and molybdenum recovery while reducing overall acid consumption. Plant feed is designed at one-million tonnes a year, with ore initially crushed before milling.

Life-of-mine uranium production is estimated at 50.8-million pounds of uranium, averaging 2.67-million pound of uranium a year over
19 years.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has an after-tax net present value, at an 8% discount rate, of $140-million and an internal rate of return of 13.3%.

Capital Expenditure
$343-million.

Planned Start/End Date
Not stated.

Latest Developments
None stated.

Key Contracts, Suppliers and Consultants
SRK Consulting and SGS Bateman (feasibility).

Contact Details for Project Information
GoviEx, tel +1 604-681-5529 or email info@goviex.com.

Edited by Martin Zhuwakinyu
Creamer Media Magazine Managing Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Sika South Africa
Sika South Africa

Sika South Africa is a trusted partner for the nation’s infrastructure, commercial, residential, and industrial sectors.

VISIT SHOWROOM 
Werner South Africa Pumps & Equipment (PTY) LTD
Werner South Africa Pumps & Equipment (PTY) LTD

For over 30 years, Werner South Africa Pumps & Equipment (PTY) LTD has been designing, manufacturing, supplying and maintaining specialist...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.051 0.808s - 146pq - 2rq
Subscribe Now