Kusile fire may delay completion of 800 MW unit by a year, warns De Ruyter
On Wednesday morning, Eskom group CEO André de Ruyter admitted to Parliament that a recent fire at unit 5 of the Kusile Power Station may delay the unit's completion by a whole year, until December 2024.
A month ago, a fire broke out at a gas air heater at unit 5, which is being commissioned and has not yet been synchronised to the grid.
De Ruyter told Parliament's Standing Committee on Public Accounts that the fire would set back Eskom’s work on the unit by a year.
"Unfortunately, I have to be open, unit number five will not be placed in commercial operation in December of 2023,” De Ruyter said. “Again, I need to emphasise that [the fire] was during the commissioning of that component and we don't believe that there was any foul play," said De Ruyter.
He said that the preliminary estimate is for a delay of 12 months, but this could be shortened following some internal "arm wrestling" in Eskom.
De Ruyter said the incident is projected to cost Eskom R150 million per month, which is related to the delays in getting the nearly 800 MW unit online much later than expected.
De Ruyter said the Eskom management would have a better understanding of the fire and its causes by the end of the weekend. He said unit six was still on track to come online in the middle of 2024.
He told the committee that Eskom management was keeping track of the costs at Kusile and Medupi.
The Eskom board approved a budget of R145 billion for the work on Medupi. "We have spent R126-billion. That gives us a R19-billion variance. We will be within that R145-billion and (for) Kusile it's still that R161.4-billion," De Ruyter said.
He said the plant defects at both Medupi and Kusile included poor performance of the pulse jet fabric filter plant due to an inadequate pulsing system, mechanical performance, erosion, furnace exit gas temperature resulting in excessive reheater spray water flow, and flue and gas ducting erosion.
Kusile and Medupi, two of the world’s biggest coal-fired power plants, were commissioned in 2007 and were supposed to be completed in 2014. But severe design defects at the two power stations are expected to take until 2027 to rectify fully.
Comments
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation