Keystone pipeline Gulf Coast expansion project, Canada and the US

9th October 2015

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

  

Font size: - +

Name and location
Keystone pipeline Gulf Coast expansion (Keystone XL) project, Canada and the US.

Client
TransCanada Corporation (TransCanada).

Project description
The Keystone XL pipeline project will enable Canadian and US oil producers to have more access to the large refining markets in the American Midwest and along the US Gulf Coast.

The project proposes a 1 897 km, 36-inch-diameter crude oil pipeline, beginning in Hardisty, Alberta, and extending south to Steele City, Nebraska, in Canada and the US respectively. This pipeline is a critical infrastructure project for the energy security of the US.

Along with transporting crude oil from Canada, the Keystone XL pipeline will also support the significant growth of crude oil production in the US from producers in the Bakken region of Montana and North Dakota.

The pipeline will have capacity to transport 830 000 bbl/d of oil to Gulf Coast and Midwest refineries, reducing American dependence on oil from Venezuela and the Middle East by up to 40%.

Value
$8-billion.

Duration
TransCanada expects to have the pipeline in service by 2015.

Latest developments
TransCanada will file an application with the Nebraska Public Service Commission (PSC) to seek approval for the Keystone XL route through the state.

TransCanada has changed tack, saying it will drop its current ‘eminent domain’ actions to force landholders to provide it access to land; it is also is taking steps to terminate constitutional court proceedings in Holt County, Nebraska.

"After careful review, we believe that going through the PSC process is the clearest path to achieving route certainty for the Keystone XL project in Nebraska. It ultimately saves time, reduces conflict with those who oppose the project and sets clear rules for approval of the route,” TransCanada president and CEO Russ Girling has stated.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Keystone XL has been delayed, owing to the rejection of TransCanada’s application for a permit to build and operate the project.

Contact Details for Project Information
TransCanada, tel +1 866 717 7473 or email keystone@transcanada.com.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Showroom

Environmental Impact Management Services
Environmental Impact Management Services

EIMS is an independent specialised environmental consulting firm offering the full spectrum of environmental management services across all sectors...

VISIT SHOWROOM 
Craig Miller Technical Services (CMTS)
Craig Miller Technical Services (CMTS)

CMTS is a leading, well-established EC&I contractor with 37+ years of mining and industrial experience. We execute full-scope EC&I projects with...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.058 1.417s - 145pq - 2rq
Subscribe Now