Kenya coal plant's power could cost ten times more, group says

11th June 2019

By: Bloomberg

  

Font size: - +

Electricity from a planned coal-fired plant in Lamu, Kenya might cost ten times as much as its developers suggest, according to an energy group that wants the project canceled.

The plant, which will require an estimated $2-billion investment, is projected to be able to produce 1 050 MW of electricity. The project is 51% owned by Nairobi-based Centum Investment, and is backed by General Electric’s so-called Ultra-Supercritical Clean Coal Technology.

Given the “realistic” costs of coal, electricity from the plant could sell for as much as $0.75/kWh on average, “more than ten times what the plant’s proponents have claimed,” Cleveland-based Institute for Energy Economics and Financial Analysis said in a report. The coal plant could also slow the East African nation’s development of renewable energy resources, IEEFA, as the group is known, said. The plant is scheduled to start marketing the power in 2024.

The current pricing estimates are based on outdated costs of imported coal and “optimistic assumptions of how much electricity the plant will generate,” according to the report. The power purchasing agreement would require payment of at least $360-million in annual capacity charges even when the plant doesn’t produce any power. “There is ample justification to cancel the entire project,” it said.

Amu Power, the developer of the project, and Kenya’s energy ministry didn’t immediately respond to text-messages seeking comment.

Edited by Bloomberg

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Showroom

Environmental Impact Management Services
Environmental Impact Management Services

EIMS is an independent specialised environmental consulting firm offering the full spectrum of environmental management services across all sectors...

VISIT SHOWROOM 
Craig Miller Technical Services (CMTS)
Craig Miller Technical Services (CMTS)

CMTS is a leading, well-established EC&I contractor with 37+ years of mining and industrial experience. We execute full-scope EC&I projects with...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.063 0.881s - 140pq - 2rq
Subscribe Now