Kakula copper mine and Kamoa-Kakula copper mine developments, Democratic Republic of Congo
Name of the Project
Kakula copper mine and Kamoa-Kakula copper mine developments.
Location
The project is located in the Kolwezi district of Lualaba province, in the Democratic Republic of Congo (DRC).
Project Owner/s
The project is a joint venture between Ivanhoe Mines, Zijin Mining Group, Crystal River Global and the DRC government.
Project Description
A prefeasibility study (PFS) on the Kakula copper mine and the expanded preliminary economic assessment (PEA) for the overall development of the Kamoa and Kakula copper discoveries at the Kamoa-Kakula project have reinforced that Kamoa-Kakula is one of world’s best undeveloped copper discoveries.
The total Kamoa-Kakula deposit hosts indicated resources of 1.39-billion tonnes grading 2.64% copper and inferred resources of 316-million grading 1.76% copper.
Kakula, which has mineral reserves of 119.7-million tonnes, benefits from an ultrahigh, average feed grade of 6.8% copper over the first five years of operations, and 5.5% copper on average over a 25-year mine life.
The Kakula 2019 PFS proposes the development of an initial six-million-tonne-a-year mine at the Kakula deposit, in the southerly portion of the Kamoa-Kakula project’s discovery area. The study envisages an average production of 291 000 t/y of copper for the first ten years of operation and yearly copper production of 360 000 t by Year 4.
Mining at the Kakula deposit will be undertaken by drift-and-fill using paste backfill, and room-and-pillar methods. About 99% of the deposit will be mined using drift-and-fill, which has been chosen to maximise the extraction of high-grade Kakula ore.
Mine access to the Kakula deposit will be through twin declines on the north side, which have been completed, and a single decline on the south side of the deposit. One of the north declines will serve as the primary mine access, while the other will include the conveyor haulage system.
The south decline will serve as a secondary operational ingress/egress and will facilitate critical early mine development.
The Kakula concentrator will be built in a phased approach with two 3-million-tonne-a-year modules as the mining operations ramp-up to full production of six-million tonnes a year. The Kakula concentrator design incor–porates a run-of-mine stockpile, followed by two stages of screening and crushing on surface.
The Kamoa-Kakula 2019 PEA presents the alternative development option of a three-phase, sequential operation on Kamoa-Kakula’s high-grade copper deposits.
Initial production is proposed to occur at six-million tonnes a year from the Kakula mine, before increasing to 12-million tonnes a year, with mill feed from the Kansoko mine. A third six-million-tonne-a year mine will then be developed at Kakula West, bringing total production to 18-million tonnes a year. As resources at Kakula and Kansoko are mined, the PEA envisages that production will begin at several mines in the Kamoa North area to maintain the 18-million-tonne-a-year throughput over a 37-year mine life.
Each mining operation is expected to be a separate underground mine with a shared processing facility and surface infrastructure located at Kakula.
Included in this scenario is the construction of a direct-to-blister flash copper smelter at the Kakula plant site, with a capacity of one-million tonnes of copper concentrate a year to be funded from internal cash flows.
This would be completed in Year 5 of operations, achieving significant savings in treatment charges and transportation costs.
The 18-million-tonne-a-year scenario delivers average production of 382 000 t/y of copper during the first ten years of operations and production of 740 000 t/y by Year 12.
Potential Job Creation
Not stated.
Net Present Value/Internal Rate of Return
The Kakula PFS estimates an after-tax net present value (NPV), at an 8% discount rate, of $5.4-billion and an internal rate of return (IRR) of 46.9%, with a project payback of 2.6 years.
The Kamoa-Kakula PEA estimates an after-tax NPV, at an 8% discount rate, of $10-billion and an IRR of 41%, with a payback of 2.9 years.
Capital Expenditure
The Kakula PFS estimates initial capital expenditure of $1.1-billion.
The Kamoa-Kakula three-phase sequential operation envisages initial capital costs of $1.1-billion.
Planned Start/End Date
Not stated.
Latest Developments
A basic engineering study is under way at the Kakula project, which is expected to be completed about midyear, running in parallel with a definitive feasibility study expected to be completed about year-end.
Meanwhile, the development of twin underground declines has been completed at Kakula, while underground development activities, including access drives and ventilation raises, are ongoing. In addition, a boxcut for a ventilation decline on the southern side of the Kakula orebody is nearing completion.
Key Contracts and Suppliers
Amec Foster Wheeler E&C Services, DRA Global, KGHM Cuprum R&D Centre, OreWin, Stantec Consulting International and SRK Consulting (PFS and PEA).
On Budget and on Time?
Not stated.
Contact Details for Project Information
Ivanhoe Mines, tel +1604688 6630 (North America)/+27 11088 4300 (South Africa) or email info@ivanhoemines.com.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation

















