JRA invests in new asphalt plant to assist in road repairs
The Johannesburg Roads Agency (JRA) has repaired 44 350 potholes across the city since the beginning of the 2017/18 financial year.
The city currently has a backlog of R11.8-billion for upgrading the city’s 13 599 km road network, of which R7.1-billion is required for repairs to surfaced roads and R4.7-billion for the upgrade of gravel roads to tar.
“Citywide, the JRA is faced with an R81.5-billion ten-year backlog to address the city’s ageing road infrastructure. Based on the 2017 JRA roads conditions study, we are faced with a 25% increase in the deterioration of the road network condition, from 89% to 64%. The excessive damage to our road network has resulted in a rise in pothole reports and increased safety concerns,” Transport MMC Nonhlanhla Makhuba said in a statement.
The JRA noted that it continued to prioritise pothole repairs, with R88-million allocated towards fast-tracking repairs and priority roads scheduled for upgrades.
Since July 2017, 520 km of roads have been resurfaced, 32.26 km upgraded from gravel roads to surfaced roads and a total of 300 m of open stormwater drains have been converted into underground systems.
In an effort to enhance service delivery, the JRA is in the process of completing the installation of a R53-million asphalt plant.
The new plant will improve efficiency and produce hot and cold tar mix through improved environment-friendly processes. It will also increase the supply of asphalt for pothole repairs and road surfacing to the JRA’s road surfacing depot and seven regional depots.
The JRA said R240-million had been allocated to resurfacing and reconstruction. The allocation is split, with R140-million for resurfacing and R100-million for reconstruction. A further R295-million has been allocated towards the upgrading of gravel roads.
“At present, 32% of surfaced roads, which make up 3 968 km, require reconstruction, 45% of surfaced roads, which make up 5 581 km, are in very good and good condition and 23% of surfaced roads, which make up 2852 km, require resurfacing,” Makhuba said.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation