Huguenot coal project, Canada
Name of the Project
Huguenot coal project.
Location
The property is located in north-east British Columbia, in Canada.
Project Owner/s
Colonial Coal.
Project Description
The updated preliminary economic assessment (PEA) on the project supports a level of confidence in the project’s potential to become a standalone operation. The project is based on conceptual openpit and underground mine plans targeting 122.3-million run-of-mine (RoM) tonnes of resource, with a yield of 73%, producing 89.3-million tonnes of clean coal over a mine life of 31 years.
The conceptual mine plan targets 56-million RoM tonnes of resource at an average stripping ratio of 8.6 :1, while the conceptual underground mine plan targets an additional 66-million RoM tonnes of resource.
The openpit is projected to operate during Years 1 to 14 while the underground mine will operate during Years 3 to 31, with both mines operating simultaneously during Years 3 to 14.
In full mine operation, projected clean coal production from combined surface and underground mining operations ranges from 1.4-million tonnes a year to 5.9-million tonnes a year, and averages about three-million tonnes a year.
Potential Job Creation
Not stated.
Net Present Value/Internal Rate of Return
The project has an after-tax net present value, at a 7.5% discount rate, of $1.17-billion and an internal rate of return of 33%, with a payback of five years from the start of operations.
Capital Expenditure
Preproduction costs are estimated at $661-million.
Planned Start/End Date
Not stated.
Latest Developments
None stated.
Key Contracts and Suppliers
Stantec Consulting Services (PEA).
On Budget and on Time?
Not stated.
Contact Details for Project Information
Colonial Coal, tel +1 604 568 4962.
Article Enquiry
Email Article
Save Article
Feedback
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation