Honeymoon uranium restart project, Australia – update
Name of the Project
Honeymoon uranium restart project.
Location
South Australia.
Project Owner/s
ASX-listed Boss Resources.
Project Description
The feasibility study has positioned Honeymoon as one of the world’s most advanced uranium development projects that can be fast-tracked to restart production in 12 months, with low capital intensity, to seize an anticipated rally in the uranium market.
The feasibility study base case has been limited to the restart area only, which comprises Joint Ore Reserves Committee-compliant resources of 36-million pounds.
The project will be completed in stages.
Stage 1 involves refurbishing the existing solvent-extraction plant, which has a nameplate capacity of 880 000 lb/y uranium equivalent.
This involves recommissioning the recently operated plant, inclusive of several key low-cost modifications to rectify the processing issues encountered by the previous owners, Uranium One Australia.
The yellowcake drying facility will be upgraded from the existing dryers to high-temperature kilns producing a calcined uranium product, which has greater market appeal.
Stage 2 is an expansion strategy that will increase production to two-million pounds a year of uranium equivalent and involves the construction of a new ion-exchange circuit. The expansion will also include additional processing infrastructure required to handle increased pregnant leach solution flow rates, and a new water treatment plant to manage increased calcium and sulphate levels in the leach liquors.
Stage 3 is not considered in this base case feasibility study, but is being investigated for the ramp-up of production capacity from two-million pounds a year of uranium equivalent to more than three-million pounds a year of uranium equivalent.
Potential Job Creation
Not stated.
Net Present Value/Internal Rate of Return
The project has a base case pretax net present value of $163-million and an internal rate of return of 42.9%, with after-tax payback (after production starts) of 4.5 years.
Capital Expenditure
The project will require a capital investment of $63.2-million.
Planned Start/End Date
Not stated.
Latest Developments
Boss Resources has confirmed that all federal and state permits required to mine, process, store, transport and export uranium from the Honeymoon operation have been received, along with permits needed to increase the nameplate production capacity to 2.45-million pounds a year.
The soon-to-be-completed enhanced feasibility study on the Honeymoon project will provide a roadmap to recommissioning, with simplified modifications.
Key Contracts, Suppliers and Consultants
None stated.
Contact Details for Project Information
Boss Resources, tel +61 8 6143 6730 or email admin@bossresources.com.au.
Article Enquiry
Email Article
Save Article
To advertise email advertising@creamermedia.co.za or click here
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation